Time Boxes are an estimating technique that sets a finite time for a task or task group. The amount of scope that is completed is variable. Whatever scope is done when the time box ends is the amount of scope for that activity on the project.
Exercise files
Download this lesson’s related exercise files.
Time-Box Estimating.docx60.1 KB Time-Box Estimating - Solution.docx
60.7 KB
Quick reference
Time Box
Time Boxes are an estimating technique that sets a finite time for a task or task group. The amount of scope that is completed is variable. Whatever scope is done when the time box ends is the amount of scope for that activity on the project.
When to use
Time Boxes are used when estimating project activities where the schedule is the most important constraint and the performance or quality level of the scope can be varied to meet the schedule.
Time Boxes are most often used on Extreme or crisis projects – or projects that are going through a short time of crisis.
Time Boxes are also used in AGILE/Scrum projects as the primary schedule estimating technique at the project level.
Instructions
- Determine the start and end date for the project or project phase.
- Based upon the total project timeline duration, allocate Time Boxes for project tasks or task groups.
- Estimates for the amount of work that can be accomplished by the individuals assigned to the tasks during the time box are generated, usually by the individuals doing the work.
- Individuals start work on the task as soon as the Time Box starts.
- Individuals work on the task or task group until the amount of time in the Time Box expires.
- Whatever level of scope achievement is created during the Time Box is by definition the level that is to be completed on the project.
Hints & tips
- Time Boxes are often considered to be the opposite of traditional project management – where the scope is defined as the project goal and as much time as is needed is used to achieve the goal. With Time Boxes, the schedule is the project goal, and whatever scope is completed is good enough for the project.
- Time Box discipline is critical. Start on time and end at the end of the Time Box.
- It is best to use dedicated resources during the Time Box.
- Keep your Time Boxes for project activities short; a good target is one to two weeks or less.