Locked lesson.
About this lesson
Earned Value Management is a comprehensive project management technique that combines scope, schedule and resource management into one set of measures. An element, in fact the element that provides the name of the technique, is the setting of Earned Value.
Exercise files
Download this lesson’s related exercise files.
Setting Earned Value.docx66.8 KB Setting Earned Value - Solution.docx
67 KB
Quick reference
Setting Earned Value
Earned Value Management is a comprehensive project management technique that combines scope, schedule and resource management into one set of measures. An element, in fact the element that provides the name of the technique, is the setting of Earned Value.
When to use
Earned value management is a very powerful technique that is particularly helpful on large complex projects. Earned value management requires a financial system that can support tracking project costs at the task level. Without this financial system, setting of “Earned Value” is meaningless. The setting of “Earned Value” is conducted at the task level. Whenever a variance analysis report is generated through the financial system, the project manager and core team will determine the “Earned Value” for each task that has been initiated since project start.
Instructions
Earned value analysis
Earned value management analyses the current and cumulative status on a project using three financial views of the project – the Planned Value (PV) which represents the project plan, the Actual Cost (AC) which is the money spent on the project as recorded in the financial system, and the Earned Value (EV) which is a project management assessment of progress made on the project.
Definition of Earned Value: "The measure of work performed expressed in terms of the budget authorized for that work." PMBOK® Guide
Explanation of earned value
Earned Value (EV) is a judgement call by the project manager and the project team concerning what portion of a task has been successfully completed. The total possible earned value for a task is based upon the original budget estimate for that task, which is the task Planned Value (PV). The percentage of a task that is completed is the percentage of value that has been “earned.” If a task is 50% complete, the task has “earned” 50% of the planned value – regardless of the cost required to get to that point. Likewise, when a task is fully complete, it has “earned” all of the value for that task, so the EV = PV. EV for a task can never exceed the PV for a task, regardless of how much has been spent. Nor can EV ever be negative.
Establishing the earned value
A risk with earned value is that someone will claim that much of the value for a task has been earned, when in reality the task has major problems and very little progress has been made. To avoid this problem, many organizations adopt rules or practices for how earned value is to be credited at the task level. This list consists of the most commonly used ones in my experience. If your organization uses a different set of practices, then follow your organizational guidelines.
- Earned value is based upon the micro-tasks within the project level task that have been completed. This is based upon value assigned to each micro-task during task-level planning. This requires detailed task planning at the micro-activity level. This will be the most accurate, but it also takes the most work, and it can be “gamed” by assigning a high PV to easy micro-tasks and a low PV to difficult micro-tasks. I normally use this approach for tasks that take longer than 2 months to complete.
- 0-100: The earned value amount is zero until the task is complete, then 100% of the PV. This is easy to use and focuses team members on getting things done. However, they are likely to start and do the easy tasks first and save the long and hard tasks for last. It is best used with tasks of one week duration or less.
- 50-50: The earned value for a task is set at 50% of the PV when the task starts and the additional 50% is credited when the task is completed. This is also easy to do and focuses the team on getting started on time. However, it can be gamed by individuals starting many tasks and doing only a little bit on each task.
- 30-70: The earned value is set at 30% of the PV for a task when the task starts and the additional 70% is credited when the task is completed. This approach is still very easy to calculate. It is meant to be a compromise between the 50-50 and the 0-100 approaches. I normally use this for tasks that are longer than a week in duration but less than 2 months.
This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
Login to downloadLesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.