Locked lesson.
About this lesson
The task board allows you to manage projects using an agile approach, where you drag-and-drop tasks from one column to another. The columns allow you to set a status for a task, like defining what tasks are next up, in progress, done, and more.
Exercise files
Download this lesson’s related exercise files.
Using the Task Board.mpp423.5 KB Using the Task Board - Completed.mpp
471.5 KB
Quick reference
The task board allows you to manage projects using an agile approach, where you drag-and-drop tasks from one column to another. The columns allow you to set a status for a task, like defining what tasks are next up, in progress, done, and more.
Steps
To access and use the task board, you will need to have at least one task in your
- Click the View tab and locate the Task Views section. Click on the Task Board icon.
- You should see at least one task on the board. Drag-and-drop tasks from one column to another.
- 00:03 In previous videos, I showed you how to update the percent complete of
- 00:08 a task either by using the percent complete,
- 00:11 using these icons up here in the Task tab, or even using the split view.
- 00:16 But if you're interested in doing things a little bit differently using a maybe more
- 00:20 Agile type approach to status in your project,
- 00:23 you can use what's called the Task Board.
- 00:25 Click the View tab, and then assuming you have project online,
- 00:30 you'll have this new Task Board icon.
- 00:33 Go ahead and click that and that will bring us into the board view.
- 00:37 In Agile, we have this concept of what's called a backlog.
- 00:41 The backlog is a list of all the items that have yet to be done.
- 00:46 And that's typically thought of in this Not Started column.
- 00:51 Now, what's a little weird with this Not Started column is Microsoft Project is
- 00:56 essentially showing us all the tasks from the project and
- 00:59 some of them may already be completed.
- 01:01 So we'll get to that in just a moment.
- 01:04 The next thing you want to do is have this Next up column.
- 01:07 This is kind of the stuff that you're planning on doing real soon.
- 01:11 Then you have In progress and Done.
- 01:14 So let's say that this Acquire land task is done, and
- 01:17 I know it is because there's a checkbox there.
- 01:20 And if I were to double-click on the box, you'd also see that
- 01:24 in the Task Information dialog, the task is 100% complete.
- 01:29 So I'm just going to go ahead and click,
- 01:31 hold on to my mouse button, and drag it over here to Done.
- 01:35 Now, I'm going to start talking to people about a few activities over
- 01:40 the course of the next few weeks.
- 01:42 So what I'm going to do is take Create architectural design and
- 01:47 Acquire loan and put those in the Next up column.
- 01:51 Now, as I'm progressing,
- 01:53 I'm realizing that someone did actually start on Create architectural design.
- 01:59 So I'll go ahead and take that and move it over here to In progress.
- 02:03 Now let's say that the Create architectural design task is done.
- 02:07 I can take this and drag it and drop it over here.
- 02:10 Notice a checkbox automatically came up here and it changed to 100%.
- 02:16 Well, wouldn't it be nice to also get a percent complete as we're dragging things
- 02:21 over rather than waiting until the end?
- 02:23 So maybe Next up to us means that it's 25% complete.
- 02:27 I'll go ahead and click the Set % Complete item and type 25, and press Enter.
- 02:34 Now the next test that I drag over will have the 25% complete, but
- 02:38 let me just show you something real quick.
- 02:40 I'm going to double-click on Acquire loan.
- 02:43 Notice it's still at 0%.
- 02:45 That's where it was before.
- 02:47 What I have to do is kind of move it back over here and then put it here.
- 02:52 And now once I've done that, I double-click again,
- 02:55 you can see the 25% complete.
- 02:57 So any other activities that we move over will now also have that 25% complete.
- 03:03 Microsoft Project allows you to also move these items around.
- 03:10 So even though the Land acquisition complete has to happen after other
- 03:14 activities, if this is an important thing for you and
- 03:17 you want to move it to the top, you can.
- 03:19 It's not going to change the layout of your project plan.
- 03:23 As a matter of fact, let's take a look at this.
- 03:25 We have Acquire loan and Acquire permits.
- 03:28 Land acquisition complete might come after those.
- 03:31 If we go back into the Gantt chart, you can see there it is,
- 03:34 Land acquisition complete happening after Acquire loan and Acquire permits.
- 03:39 So you're not really changing the structure of your project at this point.
- 03:43 You're just moving things around to put focus on the things that
- 03:46 are important to you.
- 03:47 Now, working with this backlog along the left-hand side,
- 03:50 it can get pretty daunting.
- 03:51 Look at all these activities as I scroll.
- 03:54 So another way to look at just the information you want to work with is to
- 03:59 click this filter icon on the top right.
- 04:01 Here you can see when you click on the summary item, you can just choose, for
- 04:05 example, Finalize House, and it shows you just the finalize house items.
- 04:10 Notice it also filters out the things that I had been working with before,
- 04:14 because it's focusing just on that phase of work.
- 04:17 Now I'm going to go ahead and click Prepare House Purchase.
- 04:21 And you'll notice nothing shows up on the backlog.
- 04:24 That's because all those items are already over here, so it's okay.
- 04:29 Of course, you can always just click the Clear item to clear your filter.
- 04:33 You can also filter on resources.
- 04:36 Maybe you're sitting down with, let's say the general contractor.
- 04:40 You just want to focus on the activities that the general contractor is doing
- 04:44 right now.
- 04:45 Now you can just talk to that person and drag and drop the items over as needed.
- 04:50 And then if you want to get rid of the filter altogether, you can just clear
- 04:55 that and then also click this X button to bring the screen back to normal.
- 05:00 You can also find activities by clicking on the magnifying glass.
- 05:04 And when you type it,
- 05:05 it will automatically filter everything on the screen.
- 05:08 So I'll just type purchase.
- 05:10 And you can see only those two items with P-U-R-C-H are displayed.
- 05:15 And, of course, you can click the little x item here, and
- 05:19 you'll get all of your tasks back again.
- 05:21 Finally, you can add a new column.
- 05:25 Now, why would you do that?
- 05:26 You already have Not Started, Next up, In progress, Done.
- 05:29 Well, maybe you want to have a column that's called Blocked,
- 05:33 meaning that there's a problem.
- 05:35 So I just press Enter, and now let's say that this Purchase House Materials
- 05:40 activity is blocked because we don't have access to the materials right now.
- 05:45 I can put that here, and then I can address it.
- 05:48 I can add more columns here and I can also set a percent complete.
- 05:53 I don't suggest you add many columns because then you'll end up with scrolling
- 05:57 and the screen could get a little bit too complicated.
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.