Locked lesson.
About this lesson
A Kanban Schedule is a project scheduling tool for managing a batch of similar items that must be processed through the same project steps.
Exercise files
Download this lesson’s related exercise files.
Kanban Schedule.docx.docx60.4 KB Kanban Schedule - Solution.docx.docx
62.5 KB
Quick reference
Kanban Schedule
A visual depiction of the flow of project deliverables - or mini-deliverables - through the project. Often used with the processing of a batch of items through the same steps.
When to use
The Kanban Schedule is ideal for a project that has a batch of items that must be processed through similar project management steps, such as the development of software modules or the qualification of many vendors/suppliers. It is also used as a primary scheduling tool for Agile/Scrum projects.
Instructions
Kanban schedules are displayed with two formats. The principle used for managing the schedule is identical, but the display is different. The Flow Board display is best used with small projects and with Agile/Scrum projects. The Matrix display is best used on large projects where a "batch" of items must be processed through the same project steps.
Flow board
- Decompose major deliverables into tasks.
- Each task must be tracked separately so it is documented on a unique task item.
- Place all items in the first column, representing the scope of the project plan.
- When a task is started, it is moved to the "Work In Process" column.
- When the task is finished, it is moved to the "Done" column.
- If a task becomes delayed or encounters a problem, it is moved to the "At Risk" column and receives special attention from the project manager and appropriate Core Team members.
Matrix
- Create the project schedule based upon project requirements and constraints using Milestone Charts, Gantt Charts, or Network Diagrams.
- Identify tasks that are a batch – a similar set of activities applied to multiple items.
- List the items in the first column of the matrix and the activities as column headings.
- Plan an end date for each item and activity and place it in the appropriate cell of the matrix.
- Show the batch as a single summary task on the Gantt Chart or Network Diagram.
- As the work is completed, change the background color of the cell to indicate that it is done.
Hints & tips
The approach is not appropriate on all projects, but where it is, it will save time in both planning and tracking progress and often provide a better sense of true schedule progress than any other project scheduling tool.
It is easy to calculate a "percent complete" for the project or batch by just considering the percent of tasks in the done column or of cells in the matrix that are completed. Senior management often asks for a percent complete for the project and it is very difficult to provide that from a Gantt chart or Milestone chart.
During project execution, this technique will place a spotlight on tasks or activities that are falling behind, allowing the Core Team to take early corrective action.
Login to download- 00:04 Hi, I'm Ray Sheen.
- 00:05 Let's talk about a schedule planning tool called a Kanban schedule.
- 00:09 >> This tool is a flow perspective for the project.
- 00:12 By that I mean, a group of items that all have to go through the same set of tasks
- 00:16 or activities on the project.
- 00:18 It is a visual description of how a project deliverable is flowing through
- 00:23 the various steps of the project.
- 00:25 Just like the milestone chart had two ways of showing milestones,
- 00:28 I've seen the Kanban principle applied in two different formats.
- 00:32 One is a flow board that shows the status of deliverables and the tasks supporting
- 00:36 those deliverables based upon the columns in which they are located.
- 00:40 The second is a matrix normally set up so that all the items or
- 00:44 tasks are listed down the side, creating a row in the matrix.
- 00:48 And the types of project activities are listed across the top creating
- 00:51 the columns.
- 00:52 Then the date plan for each item to complete the activity is inserted into
- 00:56 the appropriate cell in the matrix.
- 00:58 The color of the cell of the matrix is what then shows flow status.
- 01:02 These schedules create a focus on the item or activity that may be causing delays.
- 01:08 Any delay or bottleneck in the flow will become immediately apparent, and
- 01:12 the project manager and core team can take necessary action to complete that task.
- 01:17 This tool can simplify the overall project planning and tracking.
- 01:21 For adaptive or iterative projects,
- 01:23 just list the deliverable items and let the Kanban manage it.
- 01:27 And particularly if you have a batch of items that must go through the same steps,
- 01:32 show that batch on a summary task and let the Kanban track the details.
- 01:36 Let's look at the flow board view of a Kanban schedule.
- 01:39 First, decompose the deliverables into the sub tasks that must be completed.
- 01:44 These are often referred to as stories.
- 01:47 Each of these sub tasks is then individually listed so
- 01:50 it can be individually tracked.
- 01:52 Place all the sub task items in the first column that is the project plan, or
- 01:57 on an Agile scrum project it would be called the sprint backlog column.
- 02:02 Once one of the team members actually starts to work on the item,
- 02:06 then move it to the work in process column.
- 02:09 When the item is finished, move it to the finished or done column.
- 02:14 As a project leader, watch the work in process column closely.
- 02:18 If something seems to be stuck there, dig in and find out what's happening.
- 02:22 If there's a problem, move it to the at risk column and
- 02:26 put extra attention and resources on it to get it done.
- 02:30 Now, let's take a look at the matrix view of the Kanban schedule.
- 02:33 Start by creating the overall project schedule based upon the project
- 02:37 requirements and constraints.
- 02:38 I normally use a milestone chart or a high level Gantt chart or
- 02:42 network diagram for this.
- 02:44 Identify items that follow the same set of activities and can be treated as a batch.
- 02:50 Depending upon the nature of your work,
- 02:52 you may not have any items that fit this criteria.
- 02:55 In that case, don't use this tool.
- 02:58 List the items in the first column of the matrix, and
- 03:01 the activities are then listed column headings for the remaining columns.
- 03:05 Then place the plan date for when each of those items will finish each of those
- 03:09 activities in the appropriate cell of the matrix.
- 03:11 Then change the background color of the cells.
- 03:14 I use one color for those that are finished, a different color for
- 03:18 those that are late, and yet a third color for those that are in work.
- 03:21 In this example, the obvious problem is module four, and
- 03:25 it looks like coding is becoming a bottleneck.
- 03:28 I then show the batch as a single summary task on my network diagram or Gantt chart.
- 03:32 I keep the details in the matrix to simplify the other scheduling techniques.
- 03:37 There are some hints and tips we can provide for
- 03:39 using this project scheduling tool.
- 03:41 This approach will save a lot of planning time over other techniques.
- 03:46 I had a project that had approximately 80 parts that were being purchased for
- 03:50 a new product.
- 03:51 For each of those parts we had to create drawings, find a supplier,
- 03:55 qualify the supplier, set up the purchase order, conduct the first piece inspection,
- 03:59 receive the initial shipment, and initialize the inventory tracking system.
- 04:04 That's 7 steps with over 80 parts, that was more than 500 tasks.
- 04:10 But all I put into my project management software program was one summary
- 04:15 task that was several months long.
- 04:18 I managed the details with a Kanban schedule and a simple Excel spreadsheet.
- 04:23 This technique will highlight when you have an item that has fallen behind
- 04:27 schedule, the visual cue makes it easy to find and focus your attention.
- 04:31 The technique also highlights an activity that is causing problems.
- 04:35 When you see that, you know you need to focus on the bottleneck and
- 04:39 manage it closely.
- 04:40 It's easy to calculate a percent complete for the summary task.
- 04:43 In the example I just mentioned, count the number of items and
- 04:47 activities that have completed and divide this by the total number of cells,
- 04:51 in this case 560, that's the percent complete.
- 04:54 In the flow board, I use the percent of items in the done column.
- 04:58 Finally, this tool will keep the project team focused on getting things done.
- 05:04 Asking at each team meeting,
- 05:05 what has moved to the done column or which cells can be shaded in as complete,
- 05:10 emphasizes the need to keep things moving on the project.
- 05:14 >> The right project management tools are a tremendous help in the project.
- 05:18 If Kanban fits your project, then use it.
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.