Retired course
This course has been retired and is no longer supported.
About this lesson
Project quantitative risk analysis techniques provide a deeper understanding of the nature and impact of project risks.
Exercise files
Download this lesson’s related exercise files.
Quantitative Risk Analysis.docx91.6 KB Quantitative Risk Analysis - Solution.docx
290.6 KB
Quick reference
Quantitative Risk Analysis
Project quantitative risk analysis techniques provide a deeper understanding of the nature and impact of project risks.
When to use
The quantitative techniques often will take a significant amount of time to complete, ranging from hours to weeks of effort. I normally only use the quantitative techniques after I have first used a qualitative technique, such as the risk matrix. I then do a quantitative analysis for the “high” risks that require a deviation from the normal project management approach or that need a change in the project goals, objectives or boundaries in order to adequately respond. The quantitative technique provides data that can be used in justifying the risk response approach. In some cases, a quantitative analysis must be done to fulfil either industry standards or customer requirements.
Instructions
Different quantitative techniques are focused on different types of project risk and require different amounts and types of project data.
Failure Mode Effects Analysis (FMEA)
The FMEA is a quantitative technique that focuses on product technical risks. There are different variations of FMEA including Design FMEA, Process FMEA, and Application FMEA. For each technical risk in the analysis, the FMEA methodology assigns a score for the likelihood that the risk will occur, the impact to the user or customer when it occurs, and the ability of the organization or the user/customer to recognize the failure has occurred before they experience the failure. The FMEA multiplies the three scores to determine a risk priority number and the project takes actions to lower numbers above a threshold set by the business or industry.
Program Evaluation and Review Technique (PERT)
The PERT technique is a quantitative technique that focuses on cost and schedule uncertainty. The technique requires that three cost and schedule estimates be created for each task, an optimistic (best case), a pessimistic (worst case), and a most likely estimate. PERT then creates three project baselines. One baseline uses only optimistic estimates, one baseline uses only pessimistic estimates, and one baseline uses PERT estimates which are weighted average of the three estimates – with the most likely estimate receiving four times the weight of the pessimistic and optimistic. The PERT estimate for each task is calculated as:
PERT Estimate = (Optimistic + Pessimistic + (4 * Most Likely)) / 6
The optimistic and pessimistic baselines are used to explain to the stakeholders the potential project boundaries and the PERT baseline is normally used as the project baseline.
Decision Tree with EMV
The Decision Tree with EMV considers a combination of decision options and random events to create a family of project scenarios. This is the Decision Tree. Each scenario is project planned and the business impact of each scenario is determined. (This process can literally take days to create multiple project baselines.) A probability is assigned to each scenario based upon the likelihood of the random events. This probability is then multiplied times the business impact of that scenario. This calculation is the Expected Monetary Value (EMV) for that scenario. The EMV for all the scenarios that are an outgrowth of a decision are added to determine the EMV of that decision path. Normally you select the decision path with the highest EMV.
Simulations
Simulations are a computer model of the project that includes with the model the positive and negative risk events and uncertainties. Some project management software applications have simulations features or are compatible with commercially available simulation applications. A good simulation requires an accurate model of the project, a model of the uncertainty characteristics of the risk events, and the impact of the risk events on other project tasks or events. This model is then exercised in the software with the risk events occurring, or not, based upon probability factors assigned to each event. The simulation is run thousands of times using a Monte Carlo approach to assign the probability factors. Based upon the results of the thousands of runs, a forecast can be created for which risks are most significant and the impact they can cause. The modelling effort can take weeks or months for large complex projects. When working with risks for which there is little data, the model can have tremendous inaccuracies. I personally put very little trust in the models because I know that I can make a minor change to a risk parameter that will have a very significant impact – and usually there is so little real data to work with when creating the model that no one could refute that change.
Login to download
- 00:04 Hi, I'm Ray Sheen.
- 00:05 Let's talk about doing quantitative risk analysis on project risks.
- 00:10 Quantitative techniques are often used with the high risks that you're
- 00:15 escalating, these risks often require major actions or
- 00:18 boundary changes to address them.
- 00:20 And the quantitative analysis provides an in-depth understanding of the impact that
- 00:25 risk will have on the project.
- 00:28 A word of caution,
- 00:29 I normally only do quantitative risk analysis on the risks I am escalating.
- 00:33 The analysis can take hours, sometimes even days to understand just one risk.
- 00:38 Therefore I don't bother with this analysis on small risks that the team is
- 00:42 handling, but only on the big ones that I need to talk with stakeholders about, and
- 00:46 that I want to have more analysis to support the discussion.
- 00:49 There are a number of quantitative techniques that you can use.
- 00:52 In my opinion, the best ones for
- 00:54 project risks is the sensitivity analysis, the what if analysis.
- 00:59 And that’s why I dedicated an entire lesson to that technique.
- 01:01 There are other quantitative techniques that I'll briefly discuss here,
- 01:05 including the failure mode effects analysis, PERT analysis, a decision tree
- 01:09 with expected monetary value analysis, and the use of simulations.
- 01:13 Let's talk about each of these in just a little more detail.
- 01:16 First, the failure mode effects analysis or FMEA.
- 01:20 The FMEA focuses on product or process risk, not project risk,
- 01:24 it analyses whether the results of what the project creates,
- 01:28 will work as expected by the customer.
- 01:31 The product or process risk is identified, and the severity or the impact
- 01:35 of that risk on the customer and the probability of it occurring are estimated.
- 01:39 Well so far, it's just like quantifying a risk matrix.
- 01:43 But now the special part of FMEA is that the ability to control or
- 01:47 detect the risk is also rated and quantified.
- 01:51 And then these three ratings are multiplied together to calculate a risk
- 01:54 priority number.
- 01:55 If that value is too high, a risk mitigation action must be taken.
- 01:59 While FMEA is great for product or scope risk, PERT is used for schedule or
- 02:03 budget risk.
- 02:05 The program evaluation and review technique, or PERT,
- 02:08 combines a weighted average of optimistic, pessimistic, and most likely estimates
- 02:12 when there's uncertainty with the individual activity estimates.
- 02:16 You can use PERT with either budget or duration estimates.
- 02:20 To determine the PERT, start with the network diagram or flow chart of
- 02:24 the project activities, and determine the three estimates for each task.
- 02:28 I will then calculate three project schedules and budgets.
- 02:31 One using all the best case estimates, one with all the worst case estimates, and
- 02:36 the third with the PERT estimates.
- 02:38 The PERT estimate is a weighted average of the best case, worst case, and
- 02:43 four times the most likely case, all divided by 6.
- 02:47 PERT is a good tool to inform stakeholders of the magnitude of uncertainty
- 02:51 on a project.
- 02:53 If you can take a risk response action to reduce uncertainty,
- 02:56 you can bring the best case and worst case closer together, and
- 02:59 improve your ability to manage the project.
- 03:01 The next technique is a decision tree with expected monetary value.
- 03:06 The project management body of knowledge, the PMBOK Guide, defines a decision tree
- 03:10 analysis as a diagramming and calculation technique for evaluating
- 03:14 the implication of a chain of multiple events in the presence of uncertainty.
- 03:18 So let's take a look at how it works.
- 03:21 By the way, this is a favorite technique of the PMP exam.
- 03:24 So if you intend to become a project management professional,
- 03:26 make sure you know how to calculate this one.
- 03:29 The decision tree diagram is normally combined with the expected monetary value
- 03:33 analysis, or EMV, it is a product of the probability of the risks,
- 03:37 times the monetary impact of that risk.
- 03:39 Let's look at an example.
- 03:41 We have a new product that requires an investment in our factory.
- 03:43 We need to decide whether to build a new factory, or expand our existing factory.
- 03:48 If the market demand is strong, we'll need lots of capacity.
- 03:51 If the market demand is weak, we obviously won't need as much capacity.
- 03:55 Marketing has told us that there's a 60% probability of the demand being strong.
- 04:00 Well let's consider our options.
- 04:01 We'll first look at the new factory option.
- 04:04 The new factory costs $120 million to build.
- 04:07 If the demand is strong, we'll generate about $200 million of profit.
- 04:11 And if the demand is weak, only about $90 million.
- 04:14 Now to calculate EMV for the strong demand.
- 04:17 The $200 million of profit is offset by $120 million of costs, for
- 04:21 a net of $80 million.
- 04:22 We multiply that times the probability of a strong demand of 60% to get EMV of
- 04:27 $48 million.
- 04:29 For the weak demand, the net is a minus $30 million, and we multiple that
- 04:33 times the weak demand probability of 40%, for a minus $12 million.
- 04:38 Now if we add up those 2 MB's for the build new plant branch,
- 04:42 we get a total of $36 million.
- 04:44 Now we'll consider using the upgrade branch.
- 04:46 Upgrading our factory means we'll still have to live
- 04:49 with some of the current factory constraints.
- 04:52 The profit for the upgrade branch is lower because of the extra cost and
- 04:55 constraints in the old facility.
- 04:57 The net of the strong demand on the path is only $70 million, and
- 05:02 the EMV is then $42 million.
- 05:05 While the net for the weak demand is a positive $10 million,
- 05:09 and the EMV is then $4 million.
- 05:11 That means that the EMV for the upgrade path is $46 million.
- 05:15 When we compare the two paths, we see that the upgrade path has the higher total EMV.
- 05:21 Even though there's less profit with the upgrade path under both conditions of
- 05:26 a strong demand, and a weak demand, the EMV shows us that in terms of total cost
- 05:30 to the business, the upgrade path is still better.
- 05:34 The final quantitative risk analysis technique is a project simulation.
- 05:37 Simulations are computer model of the project, all activities, resources,
- 05:42 constraints, uncertainties, and risks are modeled.
- 05:45 This modeling can take a long time, and it's inherently risky,
- 05:48 since if the model is wrong, the results will be wrong,
- 05:51 and there's no way to test the model without actually doing the project.
- 05:55 The model is then run using random combinations of all the uncertainties and
- 05:59 risk factors.
- 06:00 Usually done on a Monte Carlo simulation that creates a probability distribution.
- 06:03 In our illustration, the project could take anywhere from one month
- 06:07 to six months, with a 70% probability that it will finish in three months or less.
- 06:13 The impact of specific risks can be calculated by considering how
- 06:16 the distribution function changes when different risk responses are selected.
- 06:20 Take actions on the ones that resolve your biggest problems.
- 06:24 Whichever quantitative technique you choose, you'll be able to
- 06:28 assign a numeric value to the risk, instead of just red, yellow, or green.
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.