Locked lesson.
About this lesson
Contractors, vendors, and suppliers are used on projects to reduce risks. These external resources have capacity and capability that allows them to complete project tasks better than internal resources would be able to complete them.
Exercise files
Download this lesson’s related exercise files.
Contractor Vendor Planning.docx.docx62.9 KB Contractor Vendor Planning - Solution.docx.docx
62.6 KB
Quick reference
Using Contractors and Vendors
Contractors, vendors, and suppliers are used on projects to reduce risks. These external resources have capacity and capability that allows them to complete project tasks better than internal resources would be able to complete them.
When to use
Contractors, vendors, and suppliers are normally used for one of three reasons: 1) they increase the scope and quality options on the project because they have unique skills or processes that the project team can access, 2) they are able to accelerate the project by bringing additional resources to the project beyond the internal resources, or 3) they are required to be used by customers or regulatory bodies. The tasks done by external resources should be identified during planning so that the appropriate activities and timing for source selection and procurement can be included in the plan. When a project encounters the need to do a major unplanned activity, it is often best to bring in an outside supplier or vendor to do the work and not disrupt the current planned project activities.
Instructions
Using external resources will often reduce project risk in some areas, but it adds risk in other areas. The suppliers must be managed, which takes effort, and often they are not as familiar with people, processes, and procedures which can lead to miscommunication and delays. However, these risks may be easier to manage than the risks to the project that would occur if the suppliers are not added.
Determine what project tasks can be procured from a supplier
This is done as part of scope and resource planning. Select project activities from the Work Breakdown Structure that are under-resourced or that require unique skills not found internally. Review the “Transfer” risk responses to identify other activities that should be contracted for.
Conduct a Make versus Buy analysis
The Make versus Buy analysis considers the cost and schedule impact of doing the work with internal resources and doing the same work with one or more external resources. Be certain to factor in the cost and schedule impact of procurement management activities to the “buy” options. Be certain to use realistic estimates on the availability of internal resources. Update the risk register based upon the analysis.
Determine the appropriate contract type
Select the contract type (fixed price, cost reimbursable, or time and material) and penalty and incentive clauses that are appropriate for the nature of the work and the possible risks. Remember, suppliers will perform in a manner that is best for them. Structure your contact so that what is best for them aligns with what is best for you.
Login to downloadLesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.