Locked lesson.
About this lesson
Earned Value Management is a comprehensive project management technique that combines scope, schedule and resource management into one set of measures. The Earned Value variance analysis is an analytical method for separating cost and schedule effects from financial variances.
Exercise files
Download this lesson’s related exercise files.
Earned Value Variance Analysis.docx75.3 KB Earned Value Variance Analysis - Solution.docx
79.4 KB
Quick reference
Earned Value Variance Analysis
Earned Value Management is a comprehensive project management technique that combines scope, schedule and resource management into one set of measures. The Earned Value variance analysis is an analytical method for separating cost and schedule effects from financial variances.
When to use
Variance analysis is a technique that is used as part of project control. Once a project baseline is established during project planning, the actual project performance can be compared to that baseline at any point in time in the project. Organizations using earned value management will normally conduct a variance analysis each month on each project. A variance analysis should always be done prior to developing a project forecast.
Instructions
Projects hardly ever go exactly according to plan (at least I have never had one that went exactly to plan). Some things go better than expected, some go worse. Some start early, some late, and some are just different. Variance analysis helps the project team understand why things are different than expected, and more importantly, what they should do about it, if anything.
Types of Variance
- Current period variance: this is variance in the time period of the report, typically monthly. It can be strongly impacted by tasks that are ahead or behind schedule. These tasks can drop out or come into the period. It is the difference between planned spending and actual spending during that month.
- Trend variance: this is normally a cumulative look at a type of activity from the beginning of the project or phase. This will help to cancel out variances that are due to minor schedule changes, but it can also mask important variances until they become very large. This calculation is based on determining a percentage overrun or underrun for a type of activity.
- Earned value variance: this is a set of variances that separates schedule variance effects and cost variance effects. It requires the use of a financial system that is able to collect and analyse task-level financial data.
Cost Variance
Cost variance is the underrun or overrun of actual costs as compared to the estimated project costs found in the cost baseline. When evaluating project cost variance, it is important to exclude the effect of tasks that are ahead or behind schedule. The cost baseline has embedded assumptions for which tasks will occur in which months. If a task is not worked on during a month because of a schedule delay, that could appear to be an underrun to the project for that month, since less money was spent than planned. However, if the task is accomplished the following month, it would appear to be an overrun for that month since the cost occurred in that month without any planned cost for that task occurring in that month.
The Earned Value Management approach eliminates the schedule impact on Cost Variance (CV) by using Earned Value (EV) for the baseline cost instead of Planned Value (PV). The EV represents the planned or budgeted cost for the work that has been performed. The Actual Cost (AC) is the total costs associated with doing that work. The CV then is calculated as the difference between EV and AC. A positive cost variance is an underrun and a negative cost variance is an overrun.
CV = EV - AC
Schedule Variance
Schedule variance is the ahead of schedule or behind schedule position of the project as compared to the schedule found in the schedule baseline. Schedule variance is normally presented in terms of time (days or weeks) ahead of or behind schedule. The Earned Value Management approach to schedule variance gives the variance in units of money, not time.
The Earned Value Management Schedule Variance (SV) is the estimated cost of the work that has not been done according to the project schedule plan. For work that is accomplished earlier than scheduled, this would be a positive value representing the estimate of the work accomplished early. For work that was late this is a negative value representing the estimated cost of the work that was not done when scheduled. The SV is then the difference between the EV, which is the estimated or budgeted cost of the work that has been performed and the PV which is estimated or budgeted cost of the work that should have been performed if the work was done to the baseline schedule.
SV = EV - PV
Earned Value Management variance analysis provides a clear understanding of how much variance is a schedule issue and how much is a cost issue.
Login to downloadLesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.