Locked lesson.
About this lesson
Microsoft Project provides many of the fields you need, but if you require your own, you can create them. You can even create formulas and graphical indicators.
Lesson versions
Multiple versions of this lesson are available, choose the appropriate version for you:
2013, 2019/365.
Exercise files
Download this lesson’s related exercise files.
Create Custom Fields.mpp.mpp534 KB Create Custom Fields - Completed.mpp.mpp
382 KB
Quick reference
Create Custom Fields
Microsoft Project provides many of the fields you need, but if you require your own, you can create them. You can even create formulas and graphical indicators.
Steps
To access the custom fields user interface, follow these steps:
- Click the Project tab.
- Click the Custom Fields icon.
Select a field type, rename it, and then configure it as necessary.
Login to download- 00:04 After a team meeting with the homeowner, they informed us that they're
- 00:09 concerned about the duration or the cost for the project going over 10%.
- 00:14 So as a project manager,
- 00:16 you want to create some fields that represent those requirements.
- 00:21 Now, I can go ahead and insert a field like duration variance.
- 00:25 Let me go in and insert that column right now, Duration Variance.
- 00:30 And what you can see is it shows in days.
- 00:33 But what the homeowner wants is to see this in percentages,
- 00:37 that's where custom fields come in.
- 00:40 With custom fields, you can create your own text fields, number fields,
- 00:45 date fields.
- 00:46 And you can also create formula fields, just as you would in Microsoft Excel.
- 00:51 Although it's a little bit more complicated than Excel, and I'm going to
- 00:56 show you why, and then I'm going to show you how to create the formula.
- 01:00 Before we create this duration variance formula,
- 01:03 I need to show you some quirks inside of Microsoft Project.
- 01:07 So we're going to first create our custom field.
- 01:10 Click the Project tab, locate the Properties section and
- 01:14 click the Custom Fields icon.
- 01:16 We're going to create a custom number field, so
- 01:20 choose type of Number, and make sure Task is selected.
- 01:24 We're going to use this Number1 field, so
- 01:27 these are all the empty fields that we can use.
- 01:29 We're going to start with Number1, and we're going to click Rename,
- 01:35 and call this Percent Duration Variance, and click OK.
- 01:40 Next we'll click the Formula button.
- 01:43 Now here's the quirk I want to show you,
- 01:47 I'm going to insert a field, choose Duration
- 01:52 > Baseline Duration > Baseline Duration > OK.
- 01:58 If you get any warnings, it's just telling you that it's going to overwrite data that
- 02:02 might be in the Number1 field.
- 02:03 We've never used it so it's okay, click the OK button.
- 02:07 Now first the field won't show, so we need to insert it.
- 02:14 And now you can see this 14,400, 9,600, well, what's going on here?
- 02:20 Well, when Microsoft Project looks at 1 day,
- 02:24 it treats it as 480, that's just how it stores it.
- 02:28 So if I really want to see what this value is,
- 02:34 I need to right click > Custom Fields
- 02:38 > Formula > Divide by 480 > OK.
- 02:43 So now you can see that the duration is being displayed properly.
- 02:48 Now you might see these two fields, why are they different?
- 02:50 Well, this is displaying the baseline duration, and
- 02:54 this is displaying our current duration.
- 02:56 If we recall, in a previous lesson we added ten days of duration, so
- 03:01 this is actually accurate.
- 03:03 I'm now going to update this custom field one more time,
- 03:08 so right-click > Custom Fields > Formula.
- 03:12 And I'm going to erase this value and paste in the formula.
- 03:17 Now the formula is provided in the exercise file, if you don't catch this.
- 03:21 You could also pause this lesson, so you could write this down.
- 03:25 What it's saying here is if, and this is two letter iis, so that's iif,
- 03:30 if the baseline duration is equal to zero, then just leave the value is zero.
- 03:35 Otherwise, calculate the percentage overage for the project, well,
- 03:40 actually it's a percentage of the baseline duration and the current duration.
- 03:46 Remember these divided by 40s are just there because they have to be, and
- 03:51 what those do is it requires you to put things in extra parentheses as well.
- 03:56 So we'll click the OK button.
- 03:58 But before we click OK,
- 04:00 one of the things I want to point out is currently our formula is only for tasks.
- 04:05 So project has this option here that says, how do you want to calculate summary rows?
- 04:11 So that would be the prepare new house row and
- 04:14 the my new house row as an example, choose Use Formula and click OK.
- 04:19 So now you can see we have a percentage, there's 33% over for
- 04:24 this task, we're 13% over for the overall prepare house purchase,
- 04:31 and we're 6% overall on our project as a whole.
- 04:35 I went ahead and used the same exact formula, but
- 04:39 just replaced the word duration with cost.
- 04:43 And now I have this present cost variance field that I created
- 04:47 using the Number2 field.
- 04:49 Now what you can see here is that this particular phase of work under Prepare
- 04:54 home purchase is over budget, but the Build house is slightly under budget.
- 05:00 And if you recall the reason for that is because earlier we asked the general
- 05:05 contractor to find a way to reduce the Purchase house materials task.
- 05:11 In the next lesson, I'm going to show you how to take these formulas and
- 05:14 turn them into graphical indicators.
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.