Retired course
This course has been retired and is no longer supported.
About this lesson
The monitoring and controlling processes track the project progress and implement changes and corrective actions when needed. There are twelve monitoring and controlling processes. Part 3.
Exercise files
Download this lesson’s related exercise files.
Monitoring and Controlling Process Group – Part 3.docx63 KB Monitoring and Controlling Process Group – Part 3 - Solution.docx
62.1 KB
Quick reference
Monitoring and Controlling Process Group – Part 3
The monitoring and controlling processes track the project progress and implement changes and corrective actions when needed. There are twelve monitoring and controlling processes.
When to use
Once a project has been initiated and approved, these processes are used throughout the remaining lifecycle of the project in order to ensure the project goals and objectives are achieved. They can be applied in a continuous manner or in an episodic manner. If done in an episodic manner, the episodes frequency should be rapid.
Instructions
Monitoring and Controlling Process Group
“Those processes required to track, review and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes.” PMBOK® Guide
Due to the unique nature of every project, the project activities must be monitored. The project cannot be put on “autopilot” by publishing the project plan and trusting that everything will go smoothly. The uncertainty and uniqueness of a project means that there will be aspects of the plan that are not accurate. Many of these can be addressed through the minor corrective actions of these processes. Sometime, there will need to be a larger change and new baselines created.
There are twelve processes in the Monitoring and Controlling process group. Five of those processes are addressed in this lesson and the other seven are addressed in other lessons. The five in this lesson are: Control Costs, Control Resources, Control Procurements Monitor Communications and Monitor Stakeholder Engagement.
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017 Part 2, Figure 2-1, Page 562 and Glossary definition, Page 711. |
Control Costs (7.4)
“The process of monitoring the status of the project to update the project costs and managing changes to the cost baseline.” PMBOK® Guide
Monitoring and Controlling Process Group Cost Mgmt Knowledge Area
The focus of this process is to recognize deviations to the project planned expenditures or budget baseline as soon as practicable so as to take appropriate preventive and corrective actions, thereby lowering project risk. To do this accurately, the project team must have a good understanding of what progress has been made in addition to how much money has been spent. Otherwise the project could be meeting its monthly spending goals, but falling behind in the work. At some time, the project work that is late must be done and this will turn into an overrun. This process works closely with the Perform Integrated Change Control process to ensure the budget changes are documented in the budget baseline and the impact of those changes on the other baselines has been coordinated.
Inputs:
- Project Management Plan
- Project Funding Requirements
- Work Performance Data
- Project Documents
- Organizational Process Assets
Tools and Techniques:
- Expert Judgement
- To Complete Performance Index (TCPI)
- Data Analysis
- Project Management Information System
Outputs:
- Work Performance Information
- Cost Forecasts
- Change Requests
- Project Management Plan Updates
- Project Documents Updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Figure 7-11, Page 258 and Glossary definition, Page 702. |
Control Resources (9.6)
“The process of ensuring that the physical resources assigned and allocated to the project are available as planned, as well as monitoring the planned versus actual utilization of resources and performing corrective action as necessary.” PMBOK® Guide
Monitoring and Controlling Process Group Resource Mgmt Knowledge Area
In the course of a project lifecycle, resource changes are likely. There may be changes to team members as people leave or join the organization and project team. There may also be changes in physical resources as equipment is upgraded, facilities are modified, or material usage changes from the original plan. This process tracks the application of the resources to determine their availability and effectiveness.
Inputs:
- Project Management Plan
- Agreements
- Work Performance Data
- Project Documents
- Organizational Process Assets
Tools and Techniques:
- Data Analysis
- Problem Solving
- Project Management Information System
- Interpersonal and Team Skills
Outputs:
- Work Performance Information
- Change Requests
- Project Management Plan Updates
- Project Documents Updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Figure 9-15, Page 353 and Glossary definition, Page 702. |
Control Procurements (12.3)
"The process of managing procurement relationships, monitoring contract performance, making changes and corrections as appropriate, and closing project contracts.” PMBOK® Guide
Monitoring and Controlling Process Group Procurement Mgmt Knowledge Area
The focus of this process is to ensure both buyer and seller abide by the terms of the contract. Each party wants to ensure that the legal obligations have been met. Due to the legal overtones of this process, many organizations have a separate contracts or procurement department that does this work. These individuals are trained in contract law and are able to administer the contract in accordance with the law. Project management teams may not be aware of legal provisions with which they must comply. However, contracts and procurement individuals may not be aware of the unique requirements of the project, so project managers cannot ignore this activity. The control in this process extends through to the closeout of the procurement to ensure the supplier complied with all requirements of their contract and that the appropriate payments have been made. Some projects will not be using any contracts and in that case this process is irrelevant for that project.
Inputs:
- Project Management Plan
- Procurement Documents
- Agreements
- Approved Change Requests
- Work Performance Data
- Organizational Process Assets
- Enterprise Environmental Factors
Tools and Techniques:
- Expert Judgement
- Data Analysis
- Claims Administration
- Inspections
- Audits
Outputs:
- Work Performance Information
- Change Requests
- Close Procurements
- Project Management Plan Updates
- Project Documents Updates
- Procurement Documentation Updates
- Organizational Process Assets Updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Figure 12-7, Page 493 and Glossary definition, Page 702. |
Monitor Communications (10.3)
“The process ensuring the information needs of the project and its stakeholders are met.” PMBOK® Guide
Monitoring and Controlling Process Group Communications Mgmt Knowledge Area
This process is focused on creating an optimal flow of communication within the project. It is different from the process Manage Communication which is focused on getting the right content to the right individual. This process focuses on the process of communication and ensures it is timely and efficient. The process looks for ways to improve communication and understanding between stakeholders and team members.
Inputs:
- Project Management Plan
- Work Performance Data
- Project Documents
- Organizational Process Assets
- Enterprise Environmental Factors
Tools and Techniques:
- Project Management Information Systems
- Expert Judgment
- Meetings
- Data Analysis
- Interpersonal and Team Skills
Outputs:
- Work Performance Information
- Change Requests
- Project Management Plan Updates
- Project Documents Updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Figure 10-8, Page 389 and Glossary definition, Page 711. |
Monitor Stakeholder Engagement (13.4)
“The process of monitoring project stakeholder relationships, and tailoring strategies for engaging stakeholders through the modification of engagement strategies and plans.” PMBOK® Guide
Monitoring and Controlling Process Group Stakeholder Mgmt Knowledge Area
Many project management methodologies call for regular interaction between the project team and the many different stakeholders. This process ensures that the interactions happen and that they achieve their purpose. The process ensures the stakeholder management plan is implemented and updated as required throughout the life of the project. This process is less deterministic than some because the stakeholders and their needs can be very different from project to project.
Inputs:
- Project Management Plan
- Work Performance Data
- Project Documents
- Organizational Process Assets
- Enterprise Environmental Factors
Tools and Techniques:
- Data Analysis
- Data Representation
- Decision Making
- Meetings
- Communication Skills
- Interpersonal and Team Skills
Outputs:
- Work Performance Information
- Change Requests
- Project Management Plan Updates
- Project Documents Updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Figure 13-10, Page 531 and Glossary definition, Page 711. PMBOK is a registered mark of the Project Management Institute, Inc. |
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.