Locked lesson.
About this lesson
Earned Value Management is a comprehensive project management technique that combines scope, schedule and resource management into one set of measures. It is used for planning, variance analysis and forecasting.
Exercise files
Download this lesson’s related exercise files.
Earned Value Analysis.docx255.1 KB Earned Value Analysis - Solution.docx
65.9 KB
Quick reference
Earned Value Analysis
Earned Value Management is a comprehensive project management technique that combines scope, schedule and resource management into one set of measures. It is used for planning, variance analysis and forecasting.
When to use
Earned value management is a very powerful technique that is particularly helpful on large complex projects. To conduct a thorough earned value analysis, the project must be planned and tracked in the financial system at a task level. If the financial system cannot do this, it is virtually impossible to implement earned value. If the financial system is capable, then earned value analysis can be used.
Instructions
Earned value analysis
Earned value management analyses the current and cumulative status on a project using three financial views of the project, the Planned Value (PV) which represents the project plan, the Actual Cost (AC) which is the money spent on the project as recorded in the financial system, and the Earned Value (EV) which is a project management assessment of progress made on the project. Each of these aspects of the Earned Value Management system is tracked with two time dimensions. One dimension is from the beginning of the project through the present time and is known as the “Cumulative” value. The other time dimension is for the month just completed and is known as the “Current” value.
Explanation of Planned Value
Earned value analysis starts with the Planned Value (PV). PV is the budget baseline for the project. It is established when the project is planned. Without a PV in place it is impossible to do earned value analysis. The PV should be allocated at the project task level. The budget estimate for that task is tracked in a separate cost account and the amount is spread over the weeks or months in which the task is scheduled to be accomplished.
The setting of PV is normally done by the individual responsible for that task, often referred to as a Cost Account Manager (CAM). When setting the PV, the CAM should strive to allocate the money for that task in the time periods when he or she believes it will be spent. After the allocation of project estimate has been made for each task, the sum of the PV for each month and for the total project is calculated.
The CAM typically is provided with either a “best case” value for the task or a “most likely” value. If there is an overrun on the task, the Project Manager covers that amount from his or her management reserve.
Explanation of Actual Cost
The Actual Cost (AC) is the amount of money that is spent conduct the work of a task as recorded in the company’s financial system. Depending upon the attributes of the financial system and how the work was planned by the CAM, the actual costs are divided by both project task and by a spending category such as travel, personnel, or material. The AC is the number that is recorded in the financial records of the business and is used for financial reports such as the Earnings Statement.
Explanation of Earned Value
Earned Value (EV) is a judgement call by the project manager and the CAM concerning how much of a task has been completed. The total possible earned value for a task is based upon the original budget estimate for that task, which is the task Planned Value (PV). The percentage of a task that is completed is the percentage of value that has been “earned.” If a task is 50% complete, the task has “earned” 50% of the planned value – regardless of the cost required to get to that point. Likewise, when a task is fully complete, it has “earned” all of the value for that task, so the EV = PV. EV for a task can never exceed the PV for a task, regardless of how much has been spent. Nor can EV ever be negative. The EV for a completed task is always equal to the PV. The method for establishing EV will be discussed in another module.
Login to downloadLesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.