The benefits of Lean improvements rely on changing the process schedule management approach in addition to process redesign. Pull scheduling and visual management are used to maintain smooth flow in the process.
Exercise files
Download this lesson’s related exercise files.
Lean Improvement Pull - Exercise.docx61.6 KB Lean Improvement Pull - Solution.docx
61.4 KB
Quick reference
Lean Improvement: Pull
The benefits of Lean improvements rely on changing the process schedule management approach in addition to process redesign. Pull scheduling and visual management are used to maintain smooth flow in the process.
When to use
Once the Lean flow improvements have been made to a process, it is time to consider whether to implement Pull Scheduling techniques. They are very powerful for improving customer responsiveness.
Instructions
There are two primary approaches for scheduling items to flow through a process – push scheduling and pull scheduling. Push scheduling relies on a forecasted schedule. Based upon the forecast, new items are started into the process so that they will be completing at the time of the forecasted demand. Pull scheduling relies on an actual order from a customer, based upon that demand, an item is pulled through the process.
Pull scheduling is much more responsive to customer demand, but it requires a process with a very short cycle time. Push scheduling was developed to accommodate long process cycle times. However, since the forecast is never perfectly accurate and the estimated lead times often have uncertainty, the push system is normally characterized by large amounts of unneeded inventory and inventory shortages of what customers are currently demanding.
The shortened cycle times of Lean enable many processes to operate with the flexibility and lower cost of pull scheduling and still remain responsiveness. Additionally, several techniques are used by Lean to implement pull scheduling.
Visual Scheduling
Visual scheduling is a set of scheduling principles that relies on the operators and supervisors to schedule the flow of items through a process based on the demand and how each process step is performing. The operators and supervisors are able to see all workstations in the process and can recognize when one station needs assistance and others are free. It is often used with pull scheduling because it allows everyone in the process to see what is needed next based on customer demand. There are many ways of showing the schedule needs and performance including charts, lights, and inventory containers/areas.
JIT
Just In Time inventory scheduling is an approach that can be used with either pull or push scheduling. In this approach, the materials and documentation needed to complete an item at a workstation arrive at the workstation just as work is set to begin. This reduces confusion at the workstation since there is only one item to work on. It is normally partnered with Batch Size of 1 or Kanban. When used with push scheduling, everything arrives at the workstation based on the assigned schedule time. When used with pull scheduling, items are pulled from the preceding step where they have been held in a small inventory buffer or Kanban.
Kanban
Kanban is a signal-based scheduling system that relies on a communication signal from a succeeding process step to notify it when to do the next item. It's the most popular method for implementing a pull system with visual scheduling. A visual signal is telling a particular workstation what to make and how many based on the level of usage that has occurred at the succeeding workstation. There are often lights or messages between workstations. Another common approach is to use bins, or temporary storage containers that are sent to a preceding step. When the step gets the signal container, they fill it and send it back. Most push systems using signals rely on barcode signals through ERP or other central scheduling systems.
Hints & tips
- Be creative with the visual scheduling system and Kanban, the key is a visual signal providing real-time schedule status and direction.
- Many companies have invested millions of dollars in ERP systems to plan and track manufacturing schedules. These systems are push systems. Expect resistance if you try to get “off the ERP” system and go to visual scheduling.
- The greater the uncertainty in the customer demand, the more practical and powerful is a good visual scheduling system.