Locked lesson.
About this lesson
A key element of the control plan is the response plan. It tells the process operators what to do when the process begins to deviate from the parameters laid out in the control plan.
Exercise files
Download this lesson’s related exercise files.
Response Plan Exercise.docx61.2 KB Response Plan Solution.docx
61.7 KB
Quick reference
Response Plan
A key element of the Control Plan is the Response Plan. This tells the process operators what to do when the process begins to deviate from the parameters laid out in the Control Plan.
When to use
The response plan is a portion of a control plan. When the control plan is prepared in the Control phase for release with the implementation of the new process, the response plan must be a part of it. The Response plan goes into effect when measures from the Monitoring Plan indicate a need for a response.
Instructions
The response plan is the third part of a control plan. The first two are the process documentation and the monitoring plan that explains what is to be measured, the target and limits, the responsibility for measurement, and the process for collecting the measurement information and recording the data. The response plan provides guidance to the operator on what to do when the data indicates that action is needed.
There are four process states and each requires the support of a control plan.
- The ideal state is that a process is in statistical control and delivering conforming results. The control plan should keep the process operating in this fashion.
- The threshold state is that the process is in statistical control but the process capability is poor, so some nonconforming results are produced. The process is always at the threshold of very poor performance. The control plan is essential to both keep the process centered and to provide guidance for how to disposition the non-conformances.
- The poor performance state is a process that is not in statistical control and is creating non-conforming results. When this is the case, the Lean Six Sigma project is not complete and the team needs to find solutions before considering a control plan.
- The false sense of security state is when a process is not in statistical control, but is creating conforming results. The process manager and operators may think that all is OK, but due to the presence of special cause variation, the process is not predictable and may suddenly start to create non-conforming results. Keep in mind that special cause variation can create a special condition where everything looks good, but the process cannot sustain that. A control plan is needed to recognize this situation and provide guidance to the managers and operators concerning what they should monitor and how they should respond to this.
There are five types of responses. A typical response plan will contain a combination of these, using the appropriate response based on the severity of the characteristic and the nature of the non-conformance. The five approaches are:
- Increased monitoring: This approach continues the process but with additional oversight. This is appropriate when alarm thresholds have been reached.
- Manual override: This approach is used for automated processes. The automation is stopped and the process is run manually in order to exert a little more caution.
- Stop, correct, and resume: This approach is used when the process failure is clearly identified and understood – such as maintenance and calibration failures. The operator follows the corrective action procedure and restarts the process.
- Follow special instructions: When out-of-control parameters have been identified follow instructions that were put in place for that condition.
- Stop and escalate: When out-of-control parameters have been identified and there are no special instructions, stop the process and escalate it to the experts.
Hints & tips
- Create a response for every measure and out-of-control condition. You don’t want the operators to guess what to do. Either they will do nothing or will start to tamper with the process and possibly make things worse.
- If using the “escalate” option, the subject matter experts need to respond quickly or the process management will likely override and ignore the control plan.
- The process state of the original process was determined during the Measure phase. Determine the process state of the new process with early process operation. However, be aware of the danger of the Hawthorne effect. When it is new everyone is paying special attention and it has not yet become routine.
- The Response plan actions could be a tiered response. For instance, the first tier may be a manual override and if that doesn’t work the second tier is to stop and escalate.
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.