Locked lesson.
About this lesson
The Lean process analysis will reveal flow process problems. Lean techniques can be used to analyze flow at a total process (macro) level or a process step (micro) level.
Exercise files
Download this lesson’s related exercise files.
Lean Flow Analysis - Exercise.docx63.1 KB Lean Flow Analysis - Solution.docx
139.2 KB
Quick reference
Lean Flow Analysis
The Lean process analysis will reveal flow process flow problems. Lean techniques can be used to analyze flow at both a total process (macro) level or at a process step (micro) level.
When to use
This analysis is normally done during the Analyze phase. By that time the value stream map is complete including the data in the data boxes.
Instructions
Lean flow analysis focuses on identifying those areas of the process that create flow problems such as bottlenecks or flow constraints. There are both visual and numerical analyses that can be used.
Cycle Time Map
The cycle time map shows on a linear time scale where the process is spending value-added time and where it is not. The map often further refines that analysis but adding organizational swim lanes or swim lanes for major workstations. This visual analysis technique highlights the areas of non-value-added time that are often overlooked. If total cycle time reduction is a goal for the project, it is often much easier to reduce the non-value-added time than it is to change the value-added time.
Tangled Flow
Another visual analysis approach is to look for tangled flow. If the map that was created was a process map that showed all the branches and loops, the tangled flow is immediately obvious. If a value stream map is created, the value stream will always be a straight line with no tangled flow showing. However, in this case, the indications of tangled flow can be seen by the effect that it is having on the data box values. At the point of constraint, there will often be large quantities of WIP inventory, large delays, and poor yield. Another effect that creates tangles is when item information becomes separated from the item during the process. Syncing those together again often creates a bottleneck.
TAKT
TAKT is the pulse rate of the process if it is well-designed. In an ideal process, each step is completed within the allowed TAKT time and every item moves to the next step at the same time. This simplifies scheduling and can quickly identify when there is a quality issue or other performance problem because something doesn’t move when it should. The TAKT time can be calculated by dividing the amount of time available for process work during a week by the number of items required from customer demand during a week. The resulting number is the TAKT time for each workstation.
Hints & tips
- Visual analysis tools are easier for operators and stakeholders to understand; so use them when appropriate.
- A value stream map is very useful when working with a process that regularly produces similar items. However, a process map is often better for the unusual process because it shows the tangled flow.
- If a step is longer than TAKT and can’t be shortened because of the nature of the work at that step, then the resources to do the work at that step must be increased, so that they are working multiple units in parallel. I still run with TAKT, but now I have every other resource moving their item at the pulse point.
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.