Locked lesson.
About this lesson
Learn how to view and work with tasks in Timeline view.
Exercise files
Download this lesson’s related exercise files.
5.09 make-adjustments-in-timeline-view - Exercise.docx53.5 KB 5.09 make-adjustments-in-timeline-view - Exercise solution.docx
101.1 KB
Quick reference
Durations and Timeline View
Add durations to tasks and make adjustments in Timeline View.
When to use
Durations control not only the duration of each task but also the finish date of the entire project. We need to add durations to our tasks so we have an idea of how long each task is going to take and when the project will finish.
Instructions
Our project start and finish dates won't update until we add durations to the tasks in our plan. Durations are best guess estimates as to how long a task is going to take to complete. Durations are very flexible and can be changed at any time if more or less time is required to complete a task.
Durations do not have any effect on the start date of a project but do control when a project finishes.
We can add durations to tasks in Grid view, but one of the best ways to see durations and make modifications is to view our plan in Timeline view.
Add Task Durations
We can add task duration from Grid view or Timeline view.
Add Durations in Timeline View
- Click Timeline.
Notice that we can't see any bars in Timeline view until we add durations.
- Click on Task 2.
- Click the 'i' to open the task details pane.
- In the Duration field, type '7d'.
In Project, we simply need to type 'd' for days, 'w' for weeks, 'h' for hours. Notice that the finish date of the project updates as soon as we start adding task durations.
- Close the task details pane.
Now, we can see a blue bar on the timeline that shows the duration of this task.
Add Durations in Grid View
We can also add task durations in Grid view.
- Click Grid.
- Click in the Durations column.
- Type the duration and press Enter.
Adjust Task Durations
We can adjust task durations in Timeline view by clicking on the blue bar and dragging the end of the bar in or out. The finish date of the project will update accordingly.
We can move a task to a completely different start date by clicking on the task and dragging and dropping it to a new location on the timeline.
Zoom
Once we start adding durations, we may find that the bars in Timeline view go off the page making it hard for us to see an overview of our project. We can adjust the zoom to see more or less of our project tasks.
- Use the Zoom slider at the top to adjust the page zoom.
Go to Date
We can quickly jump to a specific date in our project by clicking Go to date next to the zoom slider. We can enter a date and Project will jump to that part of the project plan.
Summary Task Durations
When we add durations to subtasks, the summary task will also show with a blue bar next to it. This bar shows the overall duration of all subtasks that belong to the summary task.
For example, if we have 3 subtasks with durations of 2, 3, and 4 days, the summary task will show a duration of 9 days in the timeline.
Hints & tips
- Durations do not include weekend days which are considered non-working time.
Lesson notes are only available for subscribers.