You add milestones to a project so you can track the completion of certain groups of tasks. Milestones are not required in a project but you will likely find them helpful when building reports or sharing the project with others.
Lesson versions
Multiple versions of this lesson are available, choose the appropriate version for you:
2013, 2019/365.
Exercise files
Download this lesson’s related exercise files.
Add Milestones to the Project.mpp335 KB Add Milestones to the Project - Completed.mpp
355 KB
Quick reference
Add Milestones to the Project
You add milestones to a project so you can track the completion of certain groups of tasks. Milestones are not required in a project but you will likely find them helpful when building reports or sharing the project with others.
Further Discussion
Very often, Project Managers create tasks to track smaller items, so they create a milestone that represents the delivery of that item (or a deliverable). For example, you might create a milestone representing a deliverable called Architectural design file delivered. Later in the project, you might create a milestone that represents the completion of all the work by the architects, like Architecture design complete.
Steps
To create a milestone in your project, follow these steps:
- Insert a new row and type key milestone complete, renaming the words key milestone with the actual name of your milestone, like move in complete.
- In the duration field, type 0d (zero days).
Note: As a general rule, adding the word complete to the end of the milestone is important.
Login to download- 00:05 At this point, we've built a detailed project schedule.
- 00:09 We have all of the tasks, durations, predecessors, and
- 00:13 resources defined for our project.
- 00:16 Something we have not done is looked at milestones and deliverables for a project.
- 00:22 So you can see here we have a lot of tasks but we only have one milestone,
- 00:26 which is essentially the end of the project.
- 00:29 It's a best practice to always have a final task that has a zero day duration,
- 00:34 making it a milestone in your project.
- 00:37 But it's also a good best practice to include milestones as you move throughout
- 00:42 the work breakdown schedule of your project.
- 00:45 So we're going to add a few milestones now.
- 00:48 Milestones are important to our project because it helps us
- 00:51 identify major areas of work that are complete.
- 00:54 We can also incorporate those into our reports as well.
- 00:58 So we wouldn't, for example, create an acquire land milestone,
- 01:03 a create architectural design milestone, and acquire loan milestone.
- 01:07 All we really need to do is create a loan that says that we've acquired the land.
- 01:12 So, let's right click on Build House, and choose Insert Task.
- 01:17 That puts a new task above Build House.
- 01:21 And here, we'll say land acquisition complete,
- 01:26 and make that zero days.
- 01:30 Let's talk a little bit about how we name milestones.
- 01:33 Just like we create tasks that have a verb, acquire, create,
- 01:40 we always want to have a milestone showing that it is complete.
- 01:45 It's a good idea to always end a milestone with the word complete.
- 01:49 If you don't use the word complete, use another word that makes sense to you, but
- 01:54 be consistent because this will show up in reports.
- 01:58 Now just like any other task in your schedule,
- 02:01 it does need to be linked to the critical path.
- 02:05 So right now, there's no tasks linking to task six.
- 02:09 I know this because I can look in the successor column and
- 02:12 see that there is a blank area here.
- 02:15 So first of all,
- 02:16 the land acquisition complete is going to be tied to task number five.
- 02:22 And I can see I have my waterfall
- 02:25 method over here on the right hand side of the screen.
- 02:28 Now, I also need to link another task to it as well.
- 02:32 And so I'm going to link task number eight to task six now.
- 02:37 And watch what happens to the successor cell in that task.
- 02:42 It linked for us.
- 02:44 And so now what I can do is I can go up and down the successors and
- 02:47 predecessors columns and make sure that there aren't any blank cells.
- 02:52 Remember we never link with summary tasks, so it's okay that these are blank.
- 02:59 I will add a milestone for every phase of work in the project.
- 03:54 At this point, you might we wondering why we didn't add these milestones earlier
- 03:59 in the estimating process.
- 04:01 Well we absolutely could have, we could put these in whenever we want.
- 04:05 However, we're getting to the point now where we have a really well estimated
- 04:09 schedule, and so what we're doing is we're putting the finishing touches on it.
- 04:13 Sometimes, adding these finishing touches, as you can see,
- 04:16 can add a little bit more work because we just inserted a few milestones, but
- 04:20 then had it to re-link predecessors and successors in our task.
- 04:24 That's okay, because as you're going through the process, you may learn
- 04:29 there's ways to optimize your schedule by re-linking different tasks.
- 04:34 So it's okay that you're adding these at the end.
- 04:36 It's a good practice to wait until you are nearly ready to start the project before
- 04:41 you add all of your milestones.
- 04:44 Now let's take a look at how we can see these milestones, and make use of them.
- 04:48 And I'm gonna show you a few different ways as we move through these lessons.
- 04:52 If you click the View tab, we’re going to look at the most obvious one,
- 04:57 which is this Filter pick list.
- 04:59 And if we choose Milestones,
- 05:01 you can see here are all the milestones under their Summary Tasks.
- 05:06 This would make for a nice little print out, report, export to PDF, or
- 05:11 just view to create when we're talking to people about what
- 05:15 the progress is of our project, and what the key milestones are.
- 05:19 To get back to the Gantt chart view, just chose this again and select no filter.