Locked lesson.
About this lesson
Baselines store certain pieces of information related to your project so you can compare your original plan to the current plan.
Lesson versions
Multiple versions of this lesson are available, choose the appropriate version for you:
2013, 2019/365.
Exercise files
Download this lesson’s related exercise files.
Create a Baseline.mpp362.5 KB Create a Baseline - Completed.mpp
443.5 KB
Quick reference
Create a Baseline
Baselines store certain pieces of information related to your project so you can compare your original plan to the current plan.
You want this feature because as your project progresses, you will change task durations, and add or remove tasks. As you do this, you will want to make sure you are not missing key dates that were agreed upon earlier in the project negotiations.
Steps
To save a baseline, follow these steps:
- Click the Project tab, click the Set Baseline icon, and then select the Set Baseline menu item.
- Set the baseline for the entire project, and then click the OK button.
- 00:04 Some congratulations are in order for you.
- 00:06 You just built your first project plan.
- 00:10 You have all of the tasks, durations, predecessors all laid out.
- 00:14 You've addressed resource overallocation issues, and
- 00:17 now it's time to start tracking your project.
- 00:20 Before you start tracking your project, what you want to do is save a baseline.
- 00:25 This way, as tasks get completed and they start early,
- 00:30 start late, you can actually do some comparisons.
- 00:34 So this way, you can tell whether or
- 00:36 not your project is on track to deliver, based on budget and schedule.
- 00:41 I'm going to show you how to set a baseline in this lesson.
- 00:45 Setting a baseline is easy.
- 00:48 Click the Project tab, locate the Schedule section,
- 00:53 click the Set Baseline icon, and then choose the Set Baseline menu item.
- 01:01 At this point, all you need to do is click the OK button, but
- 01:04 let me walk you through a few of the various settings here.
- 01:09 First, you can see there's a baseline option selected in this pick list.
- 01:14 If I expand the list, you can see that there's also a one through ten.
- 01:20 Now, most of the out-of-the-box views within Microsoft Project just use
- 01:24 baseline.
- 01:25 And what's gonna happen when we choose this,
- 01:28 is it's actually going to copy a lot of the settings, like the duration,
- 01:32 the start, the finish, to extra fields called the baseline fields.
- 01:38 This way, when we change our project,
- 01:40 we can compare our current schedule against the baseline.
- 01:45 So essentially, we're making a copy of our schedule.
- 01:48 And there's some limitations to that, which I'll discuss in a few moments.
- 01:52 There's a baseline one through ten as well.
- 01:55 I do not suggest that you use these as you get started.
- 01:59 Just focus on using the baseline.
- 02:01 As you get more advanced, you'll find various uses for these baselines.
- 02:07 There's also this option to set an interim plan.
- 02:10 And here is where you can actually set additional fields where you want to copy
- 02:15 project data.
- 02:15 We're not going to use that, because that's a more advanced topic.
- 02:20 You can also choose just selected tasks and
- 02:24 decide how you want the summaries to roll up.
- 02:26 Again, more of a advanced topic.
- 02:30 So we're just going to choose entire project.
- 02:33 And this is a setting that most people use when they use
- 02:36 the baseline feature in Project.
- 02:38 Click the OK button.
- 02:41 Nothing really exciting happened here.
- 02:43 We click the OK button and everything kind of looks the same in our project.
- 02:48 However, things aren't the same in the background.
- 02:50 As a matter of fact, every task and
- 02:53 every assignment on your project can have hundreds of fields associated with them.
- 02:59 For example, here in this Gantt Chart view we have right now, we have Task Name,
- 03:02 Duration, Predecessor, Start, Finish, Resource Name, but
- 03:07 there's hundreds more fields.
- 03:08 Let's just right-click on the Duration column and
- 03:14 choose Insert Column and type Baseline Duration and press Enter.
- 03:20 And here you can see this is a copy of the duration for our baseline.
- 03:27 So if this is our baseline, the copy, and
- 03:30 this is our working duration, our current estimate,
- 03:35 if I change this duration to let's say 40 days,
- 03:39 you can see here that this baseline duration never changed.
- 03:45 And that's because we wanna use this for comparative purposes.
- 03:50 I'll go ahead and remove Baseline Duration from this view by right-clicking and
- 03:55 choosing Hide Column.
- 03:57 When you choose Hide Column,
- 03:59 ignore this little X here that makes it look like you're deleting things.
- 04:02 You're not.
- 04:02 You're just hiding the column.
- 04:05 Let's go to the View tab.
- 04:08 And let's click the Tables pick list.
- 04:12 And choose Variance.
- 04:14 Microsoft already set up a few different views for
- 04:17 us that allow us to look at variance.
- 04:21 So if we just expand a few things here,
- 04:29 What we can see is the start date and the finish date for
- 04:33 our project, then the baseline start, and the baseline finish.
- 04:41 What you can see here is that there’s a finish of 12/1/15,
- 04:47 but the baseline finish was 11/13/2015,
- 04:52 with a finish variance of ten days.
- 04:57 Now why do all these other things say ten days?
- 05:00 Well, remember that we have a task that's red that's on the critical path.
- 05:05 So what we've essentially done is we've modified that duration and
- 05:11 it's affected all of the following tasks, right down to the end of the project.
- 05:17 So this is where the power of the baseline comes in, and I'll
- 05:21 be showing you with reports how you can even make more use of this baseline field.
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.