Locked lesson.
About this lesson
Negative Risk Response is determining what actions the project will take to address risk threats.
Exercise files
Download this lesson’s related exercise files.
Negative Risk Response.docx.docx60.7 KB Negative Risk Response - Solution.docx.docx
60 KB
Quick reference
Negative Risk Response
Negative Risk Response is determining what actions the project will take to address risk threats.
When to use
Once the risk analysis is complete (both qualitative and quantitative) risk response is prepared for all of the high (red) risks and many of the medium (yellow) risks. Typically no risk response is required for the low (green) risks.
Whenever a risk changes priority, the risk response should be reassessed.
If a risk response has been implemented in the project plan, but it is later determined to be insufficient to accommodate the risk, additional risk response should be created.
Instructions
Definition
Risk Response: “The process of developing options and actions to enhance opportunities and reduce threats to project objectives.” PMBOK® Guide
There are five approaches to Negative Risk Response. The characteristics of the organization and unique features of the project will determine which approach to use.
Escalate
This approach is used when the project team is unable to adequately address the risk with any of the other techniques. The risk is so significant that it is impacting the approved project objectives and boundaries. The team must therefore go to the stakeholder for permission to change the project objectives or boundaries in a manner that addresses this risk.
Avoid
Change the project plan so that the risk cannot happen. This requires a change in tasks or resources so that the risky aspect is no longer part of the project plan. Many risks cannot be avoided because the risky aspect of the task is a mandatory part of the project.
Mitigate
This is the most common response. This requires a change in the project plan to reduce the likelihood of the risk or the impact. The most common form of mitigation is to modify the estimate to preposition the risk response in the task estimate or to preposition a risk response task in the project. Another mitigation approach is to create a trigger event early in the project which allows a risk response to be started sooner and at lower impact.
Transfer
This requires a contract of some sort, either to ensure the project against the risk or to have an outside organization conduct part of the tasks and therefore be responsible for its completion on time and with the proper quality level.
Accept
If you do not select one of the other approaches, you are selecting accept. This approach is appropriate for very small or unlikely risks.
This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
Hints & tips
- The responses can be combined in order to get a more effective response.
- Before escalation, the project team should have attempted all of the other responses that they are able to implement.
- When the risk rating changes, the response may need to change also.
- 00:04 Hi, I'm Ray Sheen.
- 00:05 Let's talk about how to respond to threats, negative risks on your project.
- 00:10 >> The Project Management Body of Knowledge, the PMBOK Guide,
- 00:13 defines a threat risk as a risk that would have a negative effect on one or
- 00:17 more project objectives.
- 00:19 There are five different approaches you could take, escalate, avoid, mitigate,
- 00:23 transfer, and accept.
- 00:26 Which approach you take will depend upon a number of different factors associated
- 00:30 with your project or the business.
- 00:32 For instance, the type of project, project phase, resources, time and
- 00:37 money that are available, even the rationale and
- 00:40 management commitment to the project can impact which risk response you choose.
- 00:45 Let's look at each of the responses in just a little more detail.
- 00:49 One response strategy is escalate.
- 00:52 Now I'm not suggesting that this should be your first response, actually this is
- 00:57 usually the last response if none of the others will control the risk.
- 01:01 This strategy leads to a rebaseline of the project,
- 01:04 often to go down a different path which avoids or neutralizes the risk.
- 01:09 The magnitude of this risk is one that is beyond the ability of the project team to
- 01:13 address, so they bring it to the stakeholders with the request to change
- 01:17 the project goal or boundaries.
- 01:19 This risk is bigger than the team's ability to take
- 01:22 an appropriate action on it.
- 01:24 One thing the stakeholders must choose to do is to add or subtract scope.
- 01:29 Another thing is to change the project's schedule boundary,
- 01:31 like moving the project to a different fiscal year.
- 01:35 Or the stakeholders could change the project total budget, adding money or
- 01:38 moving spending between one location and another.
- 01:41 Keep in mind the stakeholders may also say that they need to find a different team.
- 01:46 The remaining four strategies are all strategies that the teams can apply
- 01:49 without asking permission from the stakeholders,
- 01:52 because the rest of the techniques do not change the overall project boundaries.
- 01:57 Let's look at the strategy avoid, this strategy removes the risk so
- 02:02 that it cannot happen.
- 02:04 This is a preventive action strategy,
- 02:06 the project plan is changed in such a way that the risk cannot occur.
- 02:11 One way to do this is to change tasks within the scope so
- 02:14 as to eliminate the tasks with the risk in it, or
- 02:17 change how that task is accomplished and controlled.
- 02:20 Another way to do this is to change the schedule so
- 02:23 that tasks happen at different times when they're not susceptible to the risk.
- 02:28 Or we can change resources by using a resource pool with different skills or
- 02:32 changing roles and responsibilities among team members.
- 02:36 A risk may be avoided.
- 02:38 One caution when using this approach, the change may eliminate one risk, but
- 02:43 there is normally new risk associated with the changed approach.
- 02:47 Be sure to add this new risk to your analysis.
- 02:50 One other point, some risks just can't be avoided so this is not always an option.
- 02:55 The next risk response strategy is mitigate.
- 02:58 Instead of a preventive action approach, we're taking an early corrective action.
- 03:02 Again, we change the project plan, but instead of avoiding the threat,
- 03:07 we prepare for it.
- 03:08 We make allowances for it within the project plan, it could still happen, but
- 03:12 it won't hurt as much.
- 03:14 We often do this by, again, changing the tasks that make up our scope or our
- 03:18 deliverables, in particular the definition of done to a different standard.
- 03:23 I often mitigate risk by changing the cost or schedule estimates.
- 03:27 I build into my estimate a risk response so I'm ready for
- 03:30 the problem when it occurs.
- 03:32 This can insulate the rest of the project from the problem,
- 03:35 isolating the impact to just that one task.
- 03:39 Another way to mitigate a risk is to create an early warning signal.
- 03:43 The sooner you know that a risk will occur, the sooner you can take action.
- 03:47 And generally, taking action early in a project will be less expensive and
- 03:51 disruptive than waiting until late in the project.
- 03:55 Finally, you can pre-position risk response capacity at a point where
- 03:59 the risk could impact the project.
- 04:02 I often do this by adding a risk mitigation task.
- 04:05 An example of this is adding a task for
- 04:08 software bug fixing in a software development project.
- 04:11 This prepositions time and
- 04:13 resources to address the unknown aspect of software bugs.
- 04:20 The next response strategy is a transfer of the risk.
- 04:23 Transferring a risk is to use some organization that is not part of
- 04:27 your organization to assume some aspect of the risk.
- 04:31 It requires a contract with that other organization, clarifying the liability and
- 04:35 exposure.
- 04:37 Some risks can be insured,
- 04:39 typically these will be things like natural disasters or damage of some type.
- 04:44 Insurance does not prevent the risk, but
- 04:46 it provides resources we can use to recover from the risk.
- 04:51 We can also transfer the risk through contract terms with a supplier,
- 04:54 such as bonds and guarantees, or using service level agreements with suppliers.
- 05:00 Even the contract type can transfer risk.
- 05:02 A fixed price contract transfers the risk of an over run to the supplier.
- 05:08 You can also transfer schedule and quality risks through penalty and
- 05:11 incentive clauses.
- 05:13 The last strategy is to use the accept approach.
- 05:17 If you haven't done one of the other four, escalate, avoid, mitigate, or transfer,
- 05:22 you are doing acceptance.
- 05:24 With this strategy, there is no immediate action on the project.
- 05:28 The project plan remains unchanged, either the threat is so small or it's so
- 05:32 uncertain you accept it for now.
- 05:35 Even though I accept the risk, I may still create a trigger.
- 05:39 That is some type of warning that this risk has grown in magnitude or
- 05:43 it has gone from being very unlikely to becoming likely.
- 05:47 If that happens, the accept strategy is changed to one of the other strategies.
- 05:53 If you have many risks that are in the accept category,
- 05:55 you should set aside a reserve to handle that.
- 05:59 This is a small amount of resources or
- 06:01 time that can be applied to these irritating small risks.
- 06:05 One final point about the accept strategy,
- 06:08 by definition accept is not a good strategy for a red risk.
- 06:13 That risk is likely to happen and it's a big deal,
- 06:16 you can't just close your eyes and accept it.
- 06:19 >> When you have a threat risk on your project you need to plan an appropriate
- 06:22 response.
- 06:23 Now whether it's escalate, avoid, mitigate, transfer, or accept,
- 06:28 select a response strategy and then implement it.
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.