Locked lesson.
About this lesson
Project plans are built with an accumulation of estimates, each of which has a level of uncertainty associated with it. The level of uncertainty is a major contributor to the accuracy of the plan and the amount of project risk.
Exercise files
Download this lesson’s related exercise files.
Estimating Uncertainty Exercise.docx.docx42 KB Estimating Uncertainty Exercise Solution.docx.docx
42 KB
Quick reference
Estimating Uncertainty
Project plans are built with an accumulation of estimates, each of which has a level of uncertainty associated with it. The level of uncertainty is a major contributor to the accuracy of the plan and the amount of project risk.
When to use
When estimating any aspect of project tasks, determine what type of uncertainty exists and then apply the appropriate estimating strategy.
When preparing or revising estimates to complete the project, determine what type of uncertainty exists and then apply the appropriate strategy.
The estimating strategy can be applied to cost estimates, time duration estimates, or level of work estimates.
Instructions
- For each task or task group, determine which category best describes the task effort on this project:
- Basic – A task that is a core competency of the organization, little uncertainty.
- Dependent – A task that is well understood but the estimate is based upon some factor that is not yet certain.
- Uncertain – A task that is not well understood, there is a high degree of uncertainty.
- Unknown – Aspects of the project for which the team has no information, there is total uncertainty.
- Depending upon the nature of the uncertainty, create the estimate.
- Basic – Use standard project estimating techniques.
- Dependent – Create an estimate of the task for each of the states of the dependent factor. Select the state that is most likely, but show the factor as a risk and monitor it as such. If the factor changes, the estimate needs to change.
- Uncertain – Estimate the best-case, worst-case, and most likely case for the task. Normally, use the most likely in the project plan, but build project reserves based upon the best case and worst case. Typically create a reserve that would cover about 75% to 80% of the worst case. This task should be tracked as a risk regardless of the estimate used.
- Unknown – The estimate is a guess and the area should be tracked as a high-risk aspect of the project.
Hints & tips
- Ignoring uncertainty does not make it go away, so acknowledge it and manage it.
- Uncertainty factors can often be managed so as to bias the actual time and money spent on a task to be close to the estimate.
- The majority of the tasks, even on high-risk projects, will be basic tasks. Have your team use standard estimating techniques on these and focus your project management attention on the other tasks.
- Uncertain tasks can often be decomposed into smaller tasks – many of which will likely be Basic tasks.
- When working on project activities with unknown tasks, do frequent pulsing checks with the project team to learn factors that can help you create an estimate.
- Definition of Estimate: “A quantitative assessment of the likely amount or outcome of a variable, such as project costs, resources, effort, or durations.” PPMBOK®Guide
This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
Login to downloadLesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.