Locked lesson.
About this lesson
Earned Value Management is a comprehensive project management technique that combines scope, schedule and resource management into one set of measures. It starts with task-level planning.
Exercise files
Download this lesson’s related exercise files.
Earned Value Planning.docx.docx256.6 KB Earned Value Planning - Solution.docx.docx
66 KB
Quick reference
Earned Value Planning
Earned Value Management is a comprehensive project management technique that combines scope, schedule, and resource management into one set of measures. It starts with task-level planning.
When to use
Earned value management is a very powerful technique that is particularly helpful on large complex predictive projects. To conduct a thorough earned value analysis, the project must be planned and tracked in the financial system at a task level. If the financial system cannot do this, it is virtually impossible to implement earned value. If the financial system is capable, then earned value planning is conducted as the project baseline plan is created and approved.
Instructions
Earned value analysis
Earned value management analyses the current and cumulative status on a project using three financial views of the project, the Planned Value (PV) which represents the project plan, the Actual Cost (AC) which is the money spent on the project as recorded in the financial system, and the Earned Value (EV) which is a project management assessment of progress made on the project.
Earned value planning
Earned value planning is the translation of the project planning information into the earned value financial system. It creates the first of three views of the project used by earned value management, the Planned Value or PV.
Creating the planned value
The PV is created using the Work Breakdown Structure (WBS), the project schedule, and the task estimates. Every task in the WBS is assigned a separate account in the financial system. The cost estimate for every WBS task is then spread over the time periods associated with the project schedule for that WBS task. Those cost amounts are placed in the WBS account for the appropriate periods to create a task-level time-phased budget estimate. This is the task PV. Once all of the task PVs are complete, they can be summed into a project PV.
When spreading the task estimate across multiple time periods, one of two techniques is used. The cost can be “level loaded.” This means the costs are spread evenly across the time periods in which the task is scheduled to be worked. The other approach to spreading the cost is “event loaded.” In this case, the WBS task is planned at a micro-level (daily or weekly) and the cost associated with the work for each micro-time period is assigned to that period and then summed to the time periods used in the financial system (normally monthly). PV is expressed either as “Current PV” which is the PV that is planned for a particular month assuming the project is on schedule, or “Cumulative PV” which is the PV from the beginning of the project to the point in time under consideration (normally the current date).
The PV is the time-phased project budget as created during project planning. The cumulative PV is often plotted on a timeline showing how much money the project expects to spend at any point in time during the project lifecycle. The total of the PV is called the Budget at Completion (BAC). This is often compared to the amount of money budgeted for the project in the Project Charter, which is called the Project Budget (PB). If the BAC is greater than the PB, the project team should immediately contact the stakeholders to request a change to the Project Charter. If the BAC is less than the PB, the project team normally holds the additional funds in an account labeled Management Reserve (MR). This money will be allocated to fund tasks that were missed during planning or to fund overruns of planned tasks.
Some software programs refer to PV as Budgeted Cost of Work Scheduled (BCWS).
Definitions
Earned Value Management: “A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.” PMBOK® Guide
Planned Value (PV): “The authorized budget assigned to scheduled work.” PMBOK® Guide
Earned Value (EV): “The measure of work performed expressed in terms of the budget authorized for that work.” PMBOK®
GuideActual Cost (AC): “The realized cost incurred for the work performed on an activity during a specific time period.” PMBOK® Guide
This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
Login to downloadLesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.