Locked lesson.
About this lesson
Earned Value Management is a comprehensive project management technique that combines scope, schedule and resource management into one set of measures. It starts with task-level planning.
Exercise files
Download this lesson’s related exercise files.
Earned Value Planning.docx.docx256.6 KB Earned Value Planning - Solution.docx.docx
66 KB
Quick reference
Earned Value Planning
Earned Value Management is a comprehensive project management technique that combines scope, schedule, and resource management into one set of measures. It starts with task-level planning.
When to use
Earned value management is a very powerful technique that is particularly helpful on large complex predictive projects. To conduct a thorough earned value analysis, the project must be planned and tracked in the financial system at a task level. If the financial system cannot do this, it is virtually impossible to implement earned value. If the financial system is capable, then earned value planning is conducted as the project baseline plan is created and approved.
Instructions
Earned value analysis
Earned value management analyses the current and cumulative status on a project using three financial views of the project, the Planned Value (PV) which represents the project plan, the Actual Cost (AC) which is the money spent on the project as recorded in the financial system, and the Earned Value (EV) which is a project management assessment of progress made on the project.
Earned value planning
Earned value planning is the translation of the project planning information into the earned value financial system. It creates the first of three views of the project used by earned value management, the Planned Value or PV.
Creating the planned value
The PV is created using the Work Breakdown Structure (WBS), the project schedule, and the task estimates. Every task in the WBS is assigned a separate account in the financial system. The cost estimate for every WBS task is then spread over the time periods associated with the project schedule for that WBS task. Those cost amounts are placed in the WBS account for the appropriate periods to create a task-level time-phased budget estimate. This is the task PV. Once all of the task PVs are complete, they can be summed into a project PV.
When spreading the task estimate across multiple time periods, one of two techniques is used. The cost can be “level loaded.” This means the costs are spread evenly across the time periods in which the task is scheduled to be worked. The other approach to spreading the cost is “event loaded.” In this case, the WBS task is planned at a micro-level (daily or weekly) and the cost associated with the work for each micro-time period is assigned to that period and then summed to the time periods used in the financial system (normally monthly). PV is expressed either as “Current PV” which is the PV that is planned for a particular month assuming the project is on schedule, or “Cumulative PV” which is the PV from the beginning of the project to the point in time under consideration (normally the current date).
The PV is the time-phased project budget as created during project planning. The cumulative PV is often plotted on a timeline showing how much money the project expects to spend at any point in time during the project lifecycle. The total of the PV is called the Budget at Completion (BAC). This is often compared to the amount of money budgeted for the project in the Project Charter, which is called the Project Budget (PB). If the BAC is greater than the PB, the project team should immediately contact the stakeholders to request a change to the Project Charter. If the BAC is less than the PB, the project team normally holds the additional funds in an account labeled Management Reserve (MR). This money will be allocated to fund tasks that were missed during planning or to fund overruns of planned tasks.
Some software programs refer to PV as Budgeted Cost of Work Scheduled (BCWS).
Definitions
Earned Value Management: “A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.” PMBOK® Guide
Planned Value (PV): “The authorized budget assigned to scheduled work.” PMBOK® Guide
Earned Value (EV): “The measure of work performed expressed in terms of the budget authorized for that work.” PMBOK®
GuideActual Cost (AC): “The realized cost incurred for the work performed on an activity during a specific time period.” PMBOK® Guide
This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
Login to download- 00:04 Hi, this is Ray Sheen, let's talk about a project management technique,
- 00:08 that's called Earned Value Analysis.
- 00:11 I'll introduce it here with resource planning and
- 00:14 we'll address it again in future courses on project control.
- 00:17 The Project Management Body Of Knowledge the PMBOK Guide describes
- 00:21 Earned Value Management as.
- 00:23 A methodology that combines scope, schedule and
- 00:26 resource measurements to assess project performance and progress.
- 00:30 In my opinion, Earned Value is one of the most effective tools we can use for
- 00:35 measuring progress on a predictive project.
- 00:38 Earned Value compares differences between three project costs perspectives.
- 00:43 The first project perspective is the project plan,
- 00:46 this is the plan costs based upon the project estimates and schedules.
- 00:49 It is created for the entire project at the time that the project planning is
- 00:54 completed, this is called Planned Value.
- 00:56 The second perspective is the Actual Cost expended on the project.
- 01:00 This will be the cost recorded in the financial system applied to the project.
- 01:05 From the time a project start until the present time, it is called Actual Cost.
- 01:11 The third perspective is the Project Progress,
- 01:14 this is an assessment by the project management team.
- 01:17 The value for the assessment is created by first determining how much progress has
- 01:22 been completed on each task.
- 01:24 That percent of completed progress on a task is then multiplied by the planned
- 01:29 cost for that task.
- 01:30 What this is essentially saying, is that when the project was planned,
- 01:35 the task was assigned a value equal to its estimate.
- 01:38 When the task is completed, it has then earned the value for that project task,
- 01:43 that's why the perspective is called the Earned Value.
- 01:47 The building block for Earned Value is at the task level,
- 01:50 it uses task level estimates or budgets for the planned value.
- 01:54 The project expenses should be collected in the financial system at the task
- 01:59 level for actual cost.
- 02:01 And the project progress is first determined at the task level and
- 02:06 this task level progress is rolled up into the total project earned value.
- 02:11 Since everything is based upon task level data,
- 02:14 it's important that the task level budgets be accurately planned.
- 02:18 This includes both the amount of cost and the timing of when those costs will occur.
- 02:22 We will be covering estimated costs and other modules of this program.
- 02:26 I want to talk now about setting the timing of the task budgets to support
- 02:31 Earned Value analysis.
- 02:32 The tasks costs must be assigned in the month in which the task occurs.
- 02:36 If the task is short, let's say a week, it's likely that all of the tasks will
- 02:41 be done within one month and then the timing is easy.
- 02:44 But what if the task is a ten week task, then what?
- 02:47 One approach is to level load the timing of the costs,
- 02:51 this means to spread the costs evenly over the duration of the task.
- 02:56 For that ten week task, if it starts at the beginning of a month,
- 02:59 put 40% in the first month, representing four weeks.
- 03:03 40% in the second month, representing another four weeks, and
- 03:06 20% in the third month representing the final two weeks.
- 03:10 This is a quick and simple method, for assigning the timing of tasks costs.
- 03:15 But what if I know,
- 03:16 there will be a high amount of costs at one point of time in the task.
- 03:20 Then do what we call event loading, in this case,
- 03:23 the task must be planned in detail.
- 03:25 Essentially breaking it into micro tasks and
- 03:28 then assigning the estimated costs for each micro task when it will occur.
- 03:33 So if I know that during the last week of that ten week task, there will be a big
- 03:38 meeting with delegates coming in from around the world for a review.
- 03:41 I would assign a higher estimated cost in that month to cover the meeting expenses.
- 03:47 The advantage of this is that it is the most accurate, since the date for
- 03:51 the planned cost matches when it will likely occur.
- 03:54 So let's wrap this up with a closer look at Earned Value Planning.
- 03:58 The Project Management Body of Knowledge, the PMBOK Guide.
- 04:02 Defines Planned Value as the authorized budget assigned to scheduled work.
- 04:06 Planned Value or PV is based upon all the task estimates for
- 04:10 all the tasks within the project scope.
- 04:13 Which is how Earned Value ties to the scope side of the triple constraint
- 04:17 triangle.
- 04:18 Of course, PV is based upon the estimated cost for each of those tasks.
- 04:23 So that is how it ties to the resource side of the project triple constraint
- 04:27 triangle.
- 04:28 And the PV for a task is scheduled to occur based upon the scheduled start and
- 04:33 completion date of each task.
- 04:36 Which is how it ties to the schedule side of the project triple constraint triangle.
- 04:41 On Project Earned Value reports, you'll find PV presented in two ways.
- 04:46 The first is the current PV, which is the estimated cost for
- 04:50 the project work that was planned to be done in the current month.
- 04:54 The second is the Cumulative PV which is the estimated costs for
- 04:58 all of the project work that is scheduled to have been done since the project start.
- 05:03 Let's look at a picture of this, this project is 19 months long.
- 05:07 As soon as the plan is approved, we know the PV for
- 05:10 each task and the project, the blue line is a graph of that cumulative PV.
- 05:16 It is the budgeted cost of all the work time phased per the project schedule.
- 05:21 The final value of PV is the budget at completion or BAC.
- 05:24 This represents the sum of the estimates of all of the identified work that must
- 05:29 be done on the project.
- 05:31 Often a project is approved with a total budget value that was a rough estimate
- 05:36 of the approval created before the detailed project plan was done.
- 05:41 This is shown by the black line across the top labeled PB for Project Budget.
- 05:46 When the detailed project plan is completed, the PV for the project is done.
- 05:50 And the budget at completion is hopefully less than that project budget.
- 05:55 The difference is a project level management reserve shown here as MR.
- 05:59 The plan value is one of the three perspectives that's used with
- 06:04 Earned Value Management.
- 06:06 The others will be covered in the course on project execution and control
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.