Locked lesson.
About this lesson
The project performance is tracked against an integrated set of project baselines that support the achievement of the project’s triple constraint goals and objectives.
Exercise files
Download this lesson’s related exercise files.
Baseline Management.docx61.2 KB Baseline Management - Solution.docx
60.3 KB
Quick reference
Baseline Management
The project performance is tracked against an integrated set of project baselines that support the achievement of the project’s triple constraint goals and objectives.
When to use
When project planning is complete, the scope, schedule, and cost baselines are established and communicated to project team members and stakeholders. As the project progresses through the project lifecycle, the actual performance is continually measured against the baseline. When required, a project change is requested from the stakeholders, and if approved, the baselines are modified to reflect the new goals, objectives, and constraints.
Instructions
We get what we measure. But to measure a project, you need to know the expectations for project performance – cost, schedule, and scope. The project baselines are the “measuring tool” for project performance. Baseline management is an integration and control activity. Risks are identified and risk resolution activities are incorporated into the baselines. A project baseline has three components, the scope baseline, the schedule baseline, and the cost (or resource) baseline. These three are integrally linked. A change in one baseline inevitably will cause a change in at least one of the other baselines.
Project control
The purpose of project control is not to ensure perfect compliance with a project plan; it is to ensure the project goals and objectives are achieved. The project plan is the project team’s intent for how to achieve the goal and objectives. The plan is expressed in the project baselines. Project performance is measured against the baselines in order to determine if the project will still be able to achieve the project goals and objectives. Variances from expected project performance could be due to under-performance or over-performance by project team members, an error in the plan, or the consequences of an unforeseen event. The project manager and core team must consider the variances, the plan, and the project objectives to determine how to react to variances. When appropriate, the reaction needs to be to modify or change the project baselines.
Project baselines
The project baselines represent the triple constraint of project management, scope, schedule, and resources. Some organizations will integrate the baselines into one comprehensive baseline, usually using the Earned Value Management system. However, most organizations do not have an integrated project management baseline methodology and instead maintain separate baselines for scope (deliverables), schedule, and cost or budget. In this case, the project manager and core team must manually integrate the baselines.
- The scope baseline is normally comprised of the scope statement, WBS, and WBS dictionary.
- The schedule baseline is normally comprised of a milestone chart or Gantt chart. (My preference is to use a milestone chart with high-level summary tasks in the baseline.)
- The cost baseline is normally the project budget, excluding management reserves but including pre-positioned risk mitigation reserves.
Some organizations also include the Core Team membership as an additional resource baseline. Baselines are controlled documents. This means changes must be approved by the designated approval authority. Many organizations will allow the project manager and core team to make minor changes but reserve major changes for approval by stakeholders. The definition of “major” and “minor” varies from organization to organization.
Definitions
- Performance Measurement Baseline (PMB): “Integrated scope, schedule, and cost baselines used for comparison to manage, measure, and control project execution.” PMBOK® Guide
- Scope Baseline: “The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.” PMBOK® Guide
- Schedule Baseline: “The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.” PMBOK® Guide
- Cost Baseline: “The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results.” PMBOK® Guide
These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
Login to downloadLesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.