Locked lesson.
About this lesson
There are several approaches a project team can take to accelerate project tasks. Each approach has its own unique characteristics and risks.
Exercise files
Download this lesson’s related exercise files.
Project Acceleration.docx63.5 KB Project Acceleration - Solution.docx
60.5 KB
Quick reference
Project Acceleration
There are several approaches a project team can take to accelerate project tasks. Each approach has its own unique characteristics and risks.
When to use
Project acceleration techniques are often applied at the time of project planning. In this case, after an initial project plan is created; the total project time from start to finish exceeds the allowed time in the project goals. The project manager and core team can apply the project acceleration techniques to create a project plan that is faster, but usually, that means it also has more risk.
Once a project plan is baselined, there are two conditions that can lead to the need to apply project acceleration techniques. In one case, a delay occurs on a project task. The project team attempts to overcome the impact of that delay by accelerating other tasks. In the other case, due to business or industry conditions, the need for project completion is accelerated. The project team must then accelerate the remaining tasks on the project.
Instructions
There are five techniques that can be used to accelerate tasks on a project. Two of the five are acknowledged by the Project Management Institute, Inc. There are two key points to keep in mind. First, acceleration techniques must be applied to critical path tasks to impact the end date of the project. It is only the critical path tasks that drive the project end date. Second, if you accelerate the critical path enough, it becomes faster than other paths and you have a new critical path.
There are very few instances in a project when all of the techniques can be used, normally only two or three of the techniques are practical. Select which technique or combination of techniques provides the lowest total risk and yet is practical from a project and organization perspective.
Float acceleration
Float acceleration is the removal of float that has been inserted into tasks or paths for risk mitigation. This often results in the creation of a “best case” schedule. This approach increases the risk of missing a targeted date. However, the accelerated completion date can be used as a target and will sometimes motivate team members to speed through tasks. For many tasks, there is no float embedded in the estimate, so the technique cannot be used on those. When there is float and the technique is used, be certain to update the risk register with the increased risk of schedule delay.
Crashing
Crashing is the application of additional resources to selected tasks to complete them sooner – in essence throwing money at the problem. Some tasks can be accelerated with extra resources. If the project has available management reserve, or if the benefit of acceleration outweighs the cost, this is a very practical acceleration technique. Crashing is a recognized technique by the Project Management Institute, Inc.
Fast tracking
Fast tracking is essentially a scope completion versus schedule trade-off. With fast tracking, a task is started before the predecessor task is fully complete. There is a “preliminary deliverable” from the predecessor task that can be used to start the next task. This allows tasks that were sequential to now overlap. This approach is not practical for all tasks but is practical when there is a “preliminary deliverable” and the resources working on the two tasks are different. The danger with this technique is if the final task deliverable of the predecessor task deviates significantly from the “preliminary deliverable,” then some of the work from the successor task may need to be repeated with the input from the final deliverable. Fast tracking is a recognized technique by the Project Management Institute, Inc.
Split releases
Split releases are a scope versus schedule trade-off. The project objectives are divided into multiple releases. One of those releases can be accelerated by diverting all the effort to complete that release. Once the first release is completed, the resources are assigned to the next release. While this accelerates the first release, it often leads to a delay in final project completion. However, if the project has multiple separable goals, this can be an effective technique for accelerating the accomplishment of at least one of the goals.
Mainline – offline scheduling
The mainline – offline scheduling technique requires that tasks on the critical path be divided into two parts. One part is that which can only be done when the unique results from a previous task are complete – the mainline subtask. The other is a portion of the task that can be done “generically” ahead of time, the offline subtask. For example, a testing task could be separated into a test setup and calibration portion that is done ahead of time and the testing of the actual device or code as soon as the device is available. By doing the offline portion ahead of time, the duration of the mainline portion is often shortened. The difficulty with this is that the analysis must be done far enough in advance to have time to do the offline portion prior to the task starting. Therefore this technique is more often used when accelerating a plan than when trying to accelerate a task while it is underway.
Login to downloadLesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.