Locked lesson.
About this lesson
Critical Path is a project scheduling technique that determines the shortest time that the current project plan can be completed.
Exercise files
Download this lesson’s related exercise files.
Critical Path.docx.docx61 KB Critical Path - Solution.docx.docx
60.6 KB
Quick reference
Critical Path
Critical Path is a project scheduling technique that determines the shortest time that the current project plan can be completed.
When to use
Critical path is used when a project is schedule-driven. In that case, the critical path is the prioritization for project tasks. If critical path tasks are delayed, the project is delayed.
Critical path is very useful when there are multiple parallel project paths. If the project is a sequential waterfall schedule, critical path provides no useful information since every task is critical. However, with multiple parallel paths, normally one path will be longer than all of the others – that is the critical path.
Critical path is often recalculated when project changes occur or if non-critical path tasks become very early or late to determine whether the critical path may have changed.
Instructions
The critical path is the most important sequence of tasks for schedule-driven projects. A delay on the critical path immediately translates into a delay to the end of the project. The only way to shorten the time on a project is to shorten the critical path. Reducing time on any tasks that are not on the critical path will speed them up but will not impact the end date of the project. When trying to complete a project as soon as possible, micro-manage the critical path.
A critical path requires that a complete network diagram is developed with all tasks included and that each task has a duration estimate. With those two elements of project planning complete, the critical path can then be calculated.
I normally calculate the critical path when the planning for a phase is being completed. If the total time is longer than I had allocated for that phase, I investigate the tasks on the critical path and determine how they can be changed to shorten the duration (reduce scope, add resources, change task relationships). I also will increase the duration estimate of tasks with technical or resource risks that are on the critical path since a problem with that task immediately creates a schedule problem in addition to the technical or resource risk.
There can be multiple critical paths within a project – when that occurs, the overall schedule risk on the project is increased since either path could lead to a delay in the project completion.
When approaching a major milestone, create or track the critical path that leads to that milestone. This will minimize the probability of a last-minute delay.
Critical Path: “The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.” PMBOK® Guide
This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
Login to download- 00:04 Hi, I'm Ray Sheen.
- 00:05 I'd like to talk about a very important element on project schedule planning
- 00:09 on schedule constrained projects and that's the critical path analysis.
- 00:14 The Project Management Body of Knowledge, the PMBOK Guide,
- 00:17 defines a critical path as the sequence of activities that represents the longest
- 00:23 path through a project, which determines the shortest possible duration.
- 00:27 That means that a critical path is the longest, but
- 00:30 not necessarily the most difficult of the project path.
- 00:33 What counts is the duration of time.
- 00:37 Let me show you an example.
- 00:38 This is a simple project network diagram.
- 00:41 There are a total of eight tasks of varying duration and
- 00:44 multiple paths through the network.
- 00:46 Let's look at the length of each of these paths.
- 00:49 If I go along the bottom path, there are three tasks, 2 days each for
- 00:54 a total of 6 days.
- 00:55 If I start in the middle and go low, there is one task of 1 day,
- 01:01 two tasks of 2 days for a total of 5 days, and 3 tasks.
- 01:06 If we follow the middle path, there are three tasks each of 1 day for
- 01:11 a total of 3 days.
- 01:12 And finally, if we follow the top path, there are only two tasks, but
- 01:17 one is 4 days and one is 3 days for a total of 7 days.
- 01:20 This path has the fewest number of tasks, but takes the longest number of days.
- 01:25 Therefore, it is the critical path.
- 01:28 Any delay to the critical path delays the project completion,
- 01:32 since all the other paths will complete before the critical path.
- 01:36 The critical path determines the final end date for the project.
- 01:40 As you might imagine, knowing your critical path is very important on
- 01:44 schedule constrained projects.
- 01:46 Critical path is normally calculated using software.
- 01:50 However, if you intend to sit for the PMP exam,
- 01:53 you should be able to do these calculations manually since you cannot
- 01:57 take any project management software into the test facility.
- 02:01 Let's take a look at how you would go about determining our critical path.
- 02:05 In order to calculate the critical path you must have completed enough of your
- 02:10 project plan to know the relationships between the tasks and
- 02:13 you must have a duration estimate for each task.
- 02:16 This means that you're able to create a network diagram showing all the tasks and
- 02:22 relationships and durations like I had on the previous slide.
- 02:26 If the project is a simple waterfall, meaning you do one task at a time,
- 02:30 the critical path analysis doesn't add much information because there's only
- 02:35 one path in the project.
- 02:36 By definition, that path is the critical path, it's the longest path through
- 02:40 the project since it's the only path through the project.
- 02:45 However, when there are multiple parallel paths,
- 02:48 the critical path analysis will determine which path is the longest and therefore
- 02:52 which path is the one that is constraining the completion of the project?
- 02:56 When the project schedule changes, the critical path might change.
- 03:00 I've been burned by this on a project.
- 03:03 We're focused on the critical path and trying to accelerate it if possible.
- 03:07 We were successful accelerating the critical path, but
- 03:10 another path was delayed and I wasn't watching it closely.
- 03:13 So although the original critical path became shorter,
- 03:16 the actual project critical path had changed and I was managing the wrong one.
- 03:21 The lesson is that when changes occur, recalculate your critical path.
- 03:25 I've said that the critical path information is very important on
- 03:29 a schedule constrained project.
- 03:31 Let's look at how we can use that information.
- 03:34 A good project manager closely manages the highest risk aspects of their project,
- 03:40 whatever those might be.
- 03:41 When the primary project constraint is schedule,
- 03:44 the highest risk aspects of the project is the critical path,
- 03:48 that is the path that will determine when the project will finish.
- 03:51 There is no schedule flexibility on the critical path.
- 03:55 All the other paths have some flexibility to accommodate issues and problems.
- 03:59 Therefore, if a problem occurs on the critical path,
- 04:02 I'll borrow resources from tasks that are underway on non critical paths.
- 04:06 If those tasks are delayed, it does not automatically mean a delay to the project.
- 04:11 But the critical path is delayed the project is delayed.
- 04:15 Another use of the critical path information is when a project is
- 04:19 approaching a major milestone.
- 04:21 I calculate and track the critical path into the milestone.
- 04:25 Often, little hiccups will occur as we approach a milestone.
- 04:29 This critical path calculation helps me to understand the impact and
- 04:33 prioritize the resolution.
- 04:34 Finally, critical path information is used to prioritize any schedule
- 04:39 acceleration techniques.
- 04:40 I apply selected techniques on the critical path in order to accelerate
- 04:45 the end date of the project.
- 04:47 Applying techniques on any non critical path does not help
- 04:50 the project complete any faster.
- 04:53 To accelerate the end of the project, you must speed up the critical path.
- 04:58 >> Understanding which tasks are on the critical path will allow the project
- 05:03 leader and the core team to make better day-to-day project management decisions.
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.