Locked lesson.
About this lesson
When risks become reality, there are major impacts both internally and externally. Risk-based design incorporates risk reduction into the design of products and processes. The sooner risks are addressed, the lower the impact of risk reduction.
Exercise files
Download this lesson’s related exercise files.
Product and Process Risk.docx61.1 KB Product and Process Risk - Solution.docx
61.4 KB
Quick reference
Product and Process Risk
Technical product or process risk will result in degrading or dangerous operational and use conditions for both operators and customers. A risk analysis should always be done during the development of new products or processes to prioritize and reduce significant risks.
When to use
Product and process risk analysis is best done as a preventive analysis to eliminate or prepare for the risk, rather than as a reactive analysis done during a crisis. New products or processes should undergo a risk analysis before design freeze, so that risk mitigation features and characteristics can be easily incorporated.
Instructions
Proactive risk management is a mindset. It relies on analysing new products and processes during the concept and design stages in order to identify risks and resolve them early. This will reduce impact on both the organization and on customers.
Design risk analysis normally creates a risk profile of potential risks and prioritizes those risks to determine which are most critical to resolve. If risks are not resolved early in the design process, later resolution often cascades into multiple problems. For instance, a problem resolved at the early concept stage may be as simple as erasing a white board and drawing a new concept. Once it moves into the preliminary design stage, the cost of resolving the problem goes up by an order of magnitude since now there are analyses to be redone and possibly some prototypes of mock-ups to rebuild. Progressing on to the next stage, once the design is frozen, the cost to implement a change to resolve a risk goes up by another order of magnitude. Now, there is the design work to be redone, but also, often the process development has started, vendors are on contract, and capital equipment has been purchased. All of these may need to change also. The cost of resolving the change goes up by another order of magnitude if the risk is not identified until after the product or service is in the market. At this time there is all the redesign effort as mentioned before, and in addition, the product or service must be recalled, repaired, or some concession provided to the customer. Sales will undoubtedly be affected. The business often has a publicity disaster on its hands that requires additional expenditures to overcome. This sequence is known as the Rule of 10’s since the cost to resolve the problem goes up by a factor of 10 as the product or service progresses through each stage.
Design risk analysis prioritizes the risks to decide which risks to address and which to accept. It is impossible to eliminate all technical risks. An analysis must be done and a business decision made as to which risks are addressed.
Technical risks can have many manifestations. The table below is an illustrative, not exhaustive list.
Hints & tips
- The risk analysis should be a structured methodology to guide the development team in their assessment. Otherwise, during the rush to develop and launch a new product or process, risks will be overlooked.
- It is often hard to get a development team to do a risk assessment. They are focused on cost and schedule of development. If they miss a risk and it is not recognized until the product or service is launched, it is usually a different set of individuals who are doing the risks response at that time.
- The Rule of 10s is a principle, not an auditable formula. In your organization, the rate of increase may be greater or less than a factor of 10.
Lesson notes are only available for subscribers.
PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.